Madinat al-Salam Drinking-Water Network (Quneitra)
Add to watchlistRehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Closure readiness
Closure planned after the forecast finish on 2026-11-12
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Eng. Wassim Al-AzmPlanned 2026-11-02
- 2
Financial closureNot started
Spend reconciled, commitments closed
Omar Al-NahhasPlanned 2026-12-02
- 3
Contract closureNot started
Contracts closed, bonds released
Omar Al-NahhasPlanned 2026-12-12
- 4
Documents archivedNot started
Documents archived with classification
Eng. Maher Al-HamawiPlanned 2026-12-07
- 5
Lessons learnedNot started
Lessons-learned session
Eng. Maher Al-HamawiPlanned 2026-11-27
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Eng. Wassim Al-AzmPlanned 2026-11-22
- 7
Final report approvedNot started
Final report and its approval
Eng. Maher Al-HamawiPlanned 2026-12-17
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2026-11-12), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
- Residents served by the rehabilitated Madinat al-Salam network
baseline 0 · now 0 · target 4,800 visitors / year
0% of target realisedHanded over at closure (current owner: Eng. Maher Al-Hamawi)