PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
PSA-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
DraftPRJ-2026-036Madinat al-Salam Drinking-Water Network (Quneitra)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1PerformanceAuto-filled

Approved budget

SYP 1.7B

Actual cost

SYP 1.6B

Cost variance

+SYP 66.3M

Schedule variance

+12 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenEng. Wassim Al-AzmFinal acceptance of every deliverable
Financial settlementOpenOmar Al-NahhasSpend reconciled, commitments closed
Contracts closedOpenOmar Al-NahhasContracts closed, bonds released
Documents archivedOpenEng. Maher Al-HamawiDocuments archived with classification
Lessons learnedOpenEng. Maher Al-HamawiLessons-learned session
Benefits handed to their ownerOpenEng. Wassim Al-AzmBenefits handed to their owner with a measurement plan
Final reportOpenEng. Maher Al-HamawiFinal report and its approval
BenefitNew ownerHandover
Residents served by the rehabilitated Madinat al-Salam networkEng. Maher Al-HamawiPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableEng. Wassim Al-Azm⁦2026-11-02⁩
Financial settlement — Spend reconciled, commitments closedOmar Al-Nahhas⁦2026-12-02⁩
Contracts closed — Contracts closed, bonds releasedOmar Al-Nahhas⁦2026-12-12⁩
Documents archived — Documents archived with classificationEng. Maher Al-Hamawi⁦2026-12-07⁩
Lessons learned — Lessons-learned sessionEng. Maher Al-Hamawi⁦2026-11-27⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planEng. Wassim Al-Azm⁦2026-11-22⁩
Final report — Final report and its approvalEng. Maher Al-Hamawi⁦2026-12-17⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Mariam Al-Zoubi

Later

Handover accepted — project owner

Eng. Wassim Al-Azm

Later

Final financial settlement

Rasha Al-Mudarres

Later

Contracts closed, guarantees released

Abdullah Al-Ujaili

Later

Project Approval Committee

Dr. Reem Al-Qabbani

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Mariam Al-Zoubi · PMO — analyst

    Delegated to Dr. Reem Al-Qabbani

  2. Technical acceptance

    Handover accepted — project owner

    Eng. Wassim Al-Azm · Project owner
  3. Financial approval

    Final financial settlement

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

  4. Financial approval

    Contracts closed, guarantees released

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee
Waiting on Eng. Maher Al-Hamawi

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Eng. Maher Al-Hamawi

Only one version so far.