Madinat al-Salam Drinking-Water Network (Quneitra)
Add to watchlistRehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-11 | 2025-03-24 | +13 days | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-07-09 | 2025-07-31 | +22 days | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-01-04 | 2026-02-11 | +38 days | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-03 | 2026-08-24 | +52 days | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-10-31 | 2026-12-08 | +38 days | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
97%Awaiting acceptance
3%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline036-D1 | 3% | CRT-036-01 | Approved | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Eng. Wassim Al-Azm | 2025-01-10 | V1 | 3 of 3 |
| Monitoring & reporting036-D2 | 3% | CRT-036-02 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-03-11 | V1 | 3 of 3 |
| Detailed design036-D3 | 6% | CRT-036-03 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-05-10 | V1 | 3 of 3 |
| Permits & approvals036-D4 | 6% | CRT-036-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2025-07-09 | V1 | 3 of 3 |
| Site works & excavation036-D5 | 13% | CRT-036-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2025-09-07 | V1 | 3 of 3 |
| Structure036-D6 | 13% | CRT-036-06 | Approved | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Eng. Wassim Al-Azm | 2025-11-05 | V1 | 3 of 3 |
| Finishes036-D7 | 13% | CRT-036-07 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-01-04 | V1 | 3 of 3 |
| Supply036-D8 | 11% | CRT-036-08 | Approved | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | Eng. Wassim Al-Azm | 2026-03-05 | V1 | 3 of 3 |
| Installation036-D9 | 11% | CRT-036-09 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-05-04 | V1 | 3 of 3 |
| Testing & commissioning036-D10 | 11% | CRT-036-10 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-07-03 | V1 | 3 of 3 |
| Provisional acceptance036-D11 | 7% | CRT-036-11 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-09-01 | V1 | 3 of 3 |
| Final acceptance036-D12 | 3% | — | Submitted | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-10-31 | V1 | 1 of 3 |
| Total · 12 | 100% |