PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-06-20⁩
ApprovedCRT-036-09Installation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The deliverableAuto-filled

DeliverableAuto-filled
Installation
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Wassim Al-Azm
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦11%⁩
DueAuto-filled
⁦2026-05-04⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-036_4.2_v1.pdfV1Eng. Wassim Al-Azm⁦2026-03-09⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Wassim Al-Azm
Accepted byAuto-filled
Salma Al-Zaim
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Testing & acceptance complete
ContractAuto-filled
CTR-2024-022
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsSubmitted—⁦2026-03-09⁩ 09:42
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-03-10⁩ 11:38
3Inspection & technical acceptance — ownerTechnical acceptanceSalma Al-ZaimProject ownerOn behalf of Eng. Wassim Al-AzmApprovedInspected and accepted against the approved acceptance criteria.⁦2026-03-11⁩ 12:45
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-03-15⁩ 12:45
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-03-16⁩ 13:22

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-03-10⁩

Inspection & technical acceptance — owner

Salma Al-Zaim

Approved⁦2026-03-11⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-03-15⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-03-16⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Wassim Al-Azm on ⁦2026-03-09⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-03-10⁩ at ⁦11:38⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2026-03-11⁩ at ⁦12:45⁩ · On behalf of Eng. Wassim Al-Azm (Salma Al-Zaim)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-03-15⁩ at ⁦12:45⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-16⁩ at ⁦13:22⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-03-09⁩

    PRJ-2026-036_4.2_v1.pdf

    Eng. Wassim Al-Azm

Only one version so far.