PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-10-31⁩
ApprovedPRJ-2026-036Madinat al-Salam Drinking-Water Network (Quneitra)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-10-06⁩

Baseline finish

⁦2026-10-31⁩

Forecast finish

⁦2026-11-12⁩

SPI

0.98

MilestonePlannedForecastSlip
Project plan approved⁦2025-03-11⁩⁦2025-03-24⁩+13 days
Designs approved⁦2025-07-09⁩⁦2025-07-31⁩+22 days
Build complete⁦2026-01-04⁩⁦2026-02-11⁩+38 days
Testing & acceptance complete⁦2026-07-03⁩⁦2026-08-24⁩+52 days
Final handover⁦2026-10-31⁩⁦2026-12-08⁩+38 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2025-01-10⁩Eng. Maher Al-Hamawi
Monitoring & reporting⁦3%⁩⁦2025-03-11⁩Eng. Wassim Al-Azm
Detailed design⁦6%⁩⁦2025-05-10⁩Eng. Wassim Al-Azm
Permits & approvals⁦6%⁩⁦2025-07-09⁩Salma Al-Zaim
Site works & excavation⁦13%⁩⁦2025-09-07⁩Salma Al-Zaim
Structure⁦13%⁩⁦2025-11-05⁩Eng. Maher Al-Hamawi
Finishes⁦13%⁩⁦2026-01-04⁩Eng. Wassim Al-Azm
Supply⁦11%⁩⁦2026-03-05⁩Eng. Maher Al-Hamawi
Installation⁦11%⁩⁦2026-05-04⁩Eng. Wassim Al-Azm
Testing & commissioning⁦11%⁩⁦2026-07-03⁩Salma Al-Zaim
Provisional acceptance⁦7%⁩⁦2026-09-01⁩Eng. Wassim Al-Azm
Final acceptance⁦3%⁩⁦2026-10-31⁩Salma Al-Zaim
Accepted with a certificate⁦97%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0045Provisional-acceptance remarks on the pumping station and control panels6MitigateEng. Maher Al-Hamawi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Maher Al-Hamawi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Maher Al-Hamawi
PMOData and indicator updatesWeeklyEng. Maher Al-Hamawi
BeneficiariesWhat changes and whenAt each milestoneEng. Maher Al-Hamawi
Team memberRoleAllocation
Eng. Maher Al-HamawiProject manager⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Residents served by the rehabilitated Madinat al-Salam network0 visitors / year4800 visitors / yearEng. Maher Al-Hamawi

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2024-10-31⁩ 13:22
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2024-11-03⁩ 09:54
3Technical acceptance — project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2024-11-05⁩ 10:01
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-11-07⁩ 14:17
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2024-11-10⁩ 09:54
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2024-11-12⁩ 13:22

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2024-11-03⁩

Technical acceptance — project owner

Eng. Wassim Al-Azm

Approved⁦2024-11-05⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2024-11-07⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2024-11-10⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2024-11-12⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2024-10-31⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-11-03⁩ at ⁦09:54⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2024-11-05⁩ at ⁦10:01⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-11-07⁩ at ⁦14:17⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-11-10⁩ at ⁦09:54⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2024-11-12⁩ at ⁦13:22⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-10-31⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Maher Al-Hamawi

  2. V1Returned for edit⁦2024-10-17⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Maher Al-Hamawi