PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP1.6B⁦17⁩ elements
Unallocated contingencySYP50.3MSYP 83.8M
Budget at completionSYP1.7BPRJ-2026-036
Weighted progress⁦97%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project793⁦2024-10-06⁩⁦2026-12-08⁩⁦97%⁩1,624.751,608.66—
1
Phase169⁦2024-10-06⁩⁦2025-03-24⁩⁦100%⁩97.4999.52—
1.1
WBS element104⁦2024-10-06⁩⁦2025-01-18⁩⁦100%⁩48.7449.760 / 1
1.2
WBS element104⁦2024-12-10⁩⁦2025-03-24⁩⁦100%⁩48.7449.761 / 2
2
Phase168⁦2025-02-13⁩⁦2025-07-31⁩⁦100%⁩194.97199.03—
2.1
WBS element103⁦2025-02-13⁩⁦2025-05-27⁩⁦100%⁩97.4999.521 / 1
2.2
WBS element103⁦2025-04-19⁩⁦2025-07-31⁩⁦100%⁩97.4999.521 / 2
3
Phase234⁦2025-06-22⁩⁦2026-02-11⁩⁦100%⁩617.41630.26—
3.1
WBS element104⁦2025-06-22⁩⁦2025-10-04⁩⁦100%⁩205.80210.091 / 1
3.2
WBS element104⁦2025-08-26⁩⁦2025-12-08⁩⁦100%⁩205.80210.091 / 1
3.3
WBS element104⁦2025-10-30⁩⁦2026-02-11⁩⁦100%⁩205.80210.091 / 2
4
Phase233⁦2026-01-03⁩⁦2026-08-24⁩⁦100%⁩487.43497.58—
4.1
WBS element104⁦2026-01-03⁩⁦2026-04-17⁩⁦100%⁩162.48165.861 / 1
4.2
WBS element103⁦2026-03-09⁩⁦2026-06-20⁩⁦100%⁩162.48165.861 / 1
4.3
WBS element103⁦2026-05-13⁩⁦2026-08-24⁩⁦100%⁩162.48165.861 / 2
5
Phase145⁦2026-07-16⁩⁦2026-12-08⁩⁦79%⁩227.47182.28—
5.1
WBS element102⁦2026-07-16⁩⁦2026-10-26⁩⁦100%⁩113.73116.101 / 1
5.2
WBS element134⁦2026-07-27⁩⁦2026-12-08⁩⁦57%⁩113.7366.181 / 1
Total⁦97%⁩1,624.751,608.66