Madinat al-Salam Drinking-Water Network (Quneitra) Subtask Last item under this branch 2026-12-08 97% Madinat al-Salam Drinking-Water Network (Quneitra) Planned: 2024-10-06 → 2026-10-31 Forecast: 2024-10-06 → 2026-12-08 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-03-24 100% Management & governance Planned: 2024-10-06 → 2025-03-11 Actual: 2024-10-06 → 2025-03-24
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-01-18 100% Project plan & baseline Planned: 2024-10-06 → 2025-01-10 Actual: 2024-10-06 → 2025-01-18
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-24 100% Monitoring & reporting Planned: 2024-12-05 → 2025-03-11 Actual: 2024-12-10 → 2025-03-24
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-24 100% Project plan approved Planned: 2025-03-11 → 2025-03-11 Actual: 2025-03-24 → 2025-03-24 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-07-31 100% Design & permits Planned: 2025-02-03 → 2025-07-09 Actual: 2025-02-13 → 2025-07-31
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-27 100% Detailed design Planned: 2025-02-03 → 2025-05-10 Actual: 2025-02-13 → 2025-05-27
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-31 100% Permits & approvals Planned: 2025-04-04 → 2025-07-09 Actual: 2025-04-19 → 2025-07-31
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-31 100% Designs approved Planned: 2025-07-09 → 2025-07-09 Actual: 2025-07-31 → 2025-07-31 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-02-11 100% Civil works Planned: 2025-06-03 → 2026-01-04 Actual: 2025-06-22 → 2026-02-11
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-04 100% Site works & excavation Planned: 2025-06-03 → 2025-09-07 Actual: 2025-06-22 → 2025-10-04
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-08 100% Structure Planned: 2025-08-02 → 2025-11-05 Actual: 2025-08-26 → 2025-12-08
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-11 100% Finishes Planned: 2025-10-01 → 2026-01-04 Actual: 2025-10-30 → 2026-02-11
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-11 100% Build complete Planned: 2026-01-04 → 2026-01-04 Actual: 2026-02-11 → 2026-02-11 Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-08-24 100% MEP works Planned: 2025-11-29 → 2026-07-03 Actual: 2026-01-03 → 2026-08-24
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-17 100% Supply Planned: 2025-11-29 → 2026-03-05 Actual: 2026-01-03 → 2026-04-17
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-20 100% Installation Planned: 2026-01-28 → 2026-05-04 Actual: 2026-03-09 → 2026-06-20
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-24 100% Testing & commissioning Planned: 2026-03-29 → 2026-07-03 Actual: 2026-05-13 → 2026-08-24
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-24 100% Testing & acceptance complete Planned: 2026-07-03 → 2026-07-03 Actual: 2026-08-24 → 2026-08-24 Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-08 79% Handover Planned: 2026-05-28 → 2026-10-31 Forecast: 2026-07-16 → 2026-12-08 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Provisional acceptance Planned: 2026-05-28 → 2026-09-01 Actual: 2026-07-16 → 2026-10-26
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-08 57% Final acceptance Planned: 2026-07-27 → 2026-10-31 Forecast: 2026-07-27 → 2026-12-08 Float: 0d Drag to change its duration +38
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-08 0% Final handover Planned: 2026-10-31 → 2026-10-31 Forecast: 2026-12-08 → 2026-12-08 Float: 0d Drag to change its dates Final handover