Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+38⁩ days vs approved

Baseline (original = approved)⁦2026-10-31⁩
Current forecast⁦2026-12-08⁩
By earned schedule⁦2027-01-25⁩
Critical activities
2
of ⁦2⁩ open activities
Late activities
1
past their baseline finish
Schedule performance
0.97
earned ÷ planned value
Next milestone
in 41 days
Final handover
Expand allCollapse all
Activity
Madinat al-Salam Drinking-Water Network (Quneitra)Planned: ⁦2024-10-06⁩ → ⁦2026-10-31⁩Forecast: ⁦2024-10-06⁩ → ⁦2026-12-08⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2024-10-06⁩ → ⁦2025-03-11⁩Actual: ⁦2024-10-06⁩ → ⁦2025-03-24⁩
Project plan & baselinePlanned: ⁦2024-10-06⁩ → ⁦2025-01-10⁩Actual: ⁦2024-10-06⁩ → ⁦2025-01-18⁩
Monitoring & reportingPlanned: ⁦2024-12-05⁩ → ⁦2025-03-11⁩Actual: ⁦2024-12-10⁩ → ⁦2025-03-24⁩
Project plan approvedPlanned: ⁦2025-03-11⁩ → ⁦2025-03-11⁩Actual: ⁦2025-03-24⁩ → ⁦2025-03-24⁩Project plan approved
Design & permitsPlanned: ⁦2025-02-03⁩ → ⁦2025-07-09⁩Actual: ⁦2025-02-13⁩ → ⁦2025-07-31⁩
Detailed designPlanned: ⁦2025-02-03⁩ → ⁦2025-05-10⁩Actual: ⁦2025-02-13⁩ → ⁦2025-05-27⁩
Permits & approvalsPlanned: ⁦2025-04-04⁩ → ⁦2025-07-09⁩Actual: ⁦2025-04-19⁩ → ⁦2025-07-31⁩
Designs approvedPlanned: ⁦2025-07-09⁩ → ⁦2025-07-09⁩Actual: ⁦2025-07-31⁩ → ⁦2025-07-31⁩Designs approved
Civil worksPlanned: ⁦2025-06-03⁩ → ⁦2026-01-04⁩Actual: ⁦2025-06-22⁩ → ⁦2026-02-11⁩
Site works & excavationPlanned: ⁦2025-06-03⁩ → ⁦2025-09-07⁩Actual: ⁦2025-06-22⁩ → ⁦2025-10-04⁩
StructurePlanned: ⁦2025-08-02⁩ → ⁦2025-11-05⁩Actual: ⁦2025-08-26⁩ → ⁦2025-12-08⁩
FinishesPlanned: ⁦2025-10-01⁩ → ⁦2026-01-04⁩Actual: ⁦2025-10-30⁩ → ⁦2026-02-11⁩
Build completePlanned: ⁦2026-01-04⁩ → ⁦2026-01-04⁩Actual: ⁦2026-02-11⁩ → ⁦2026-02-11⁩Build complete
MEP worksPlanned: ⁦2025-11-29⁩ → ⁦2026-07-03⁩Actual: ⁦2026-01-03⁩ → ⁦2026-08-24⁩
SupplyPlanned: ⁦2025-11-29⁩ → ⁦2026-03-05⁩Actual: ⁦2026-01-03⁩ → ⁦2026-04-17⁩
InstallationPlanned: ⁦2026-01-28⁩ → ⁦2026-05-04⁩Actual: ⁦2026-03-09⁩ → ⁦2026-06-20⁩
Testing & commissioningPlanned: ⁦2026-03-29⁩ → ⁦2026-07-03⁩Actual: ⁦2026-05-13⁩ → ⁦2026-08-24⁩
Testing & acceptance completePlanned: ⁦2026-07-03⁩ → ⁦2026-07-03⁩Actual: ⁦2026-08-24⁩ → ⁦2026-08-24⁩Testing & acceptance complete
HandoverPlanned: ⁦2026-05-28⁩ → ⁦2026-10-31⁩Forecast: ⁦2026-07-16⁩ → ⁦2026-12-08⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-05-28⁩ → ⁦2026-09-01⁩Actual: ⁦2026-07-16⁩ → ⁦2026-10-26⁩
Final acceptancePlanned: ⁦2026-07-27⁩ → ⁦2026-10-31⁩Forecast: ⁦2026-07-27⁩ → ⁦2026-12-08⁩Float: ⁦0⁩dDrag to change its duration+38
Final handoverPlanned: ⁦2026-10-31⁩ → ⁦2026-10-31⁩Forecast: ⁦2026-12-08⁩ → ⁦2026-12-08⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦2⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦1⁩ activity with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 33 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

13
22
38
52
38
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close