Madinat al-Salam Drinking-Water Network (Quneitra)
Add to watchlistRehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage