Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-12-08⁩
ApprovedCRT-036-06Structure

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The deliverableAuto-filled

DeliverableAuto-filled
Structure
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Maher Al-Hamawi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦13%⁩
DueAuto-filled
⁦2025-11-05⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-036_3.2_v1.pdfV1Eng. Maher Al-Hamawi⁦2025-08-26⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Wassim Al-Azm
Accepted byAuto-filled
Salma Al-Zaim
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2024-022
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2025-08-26⁩ 12:21
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-08-28⁩ 14:47
3Inspection & technical acceptance — ownerTechnical acceptanceSalma Al-ZaimProject ownerOn behalf of Eng. Wassim Al-AzmApprovedInspected and accepted against the approved acceptance criteria.⁦2025-08-31⁩ 09:54
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-09-01⁩ 09:24
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-09-03⁩ 10:01

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2025-08-28⁩

Inspection & technical acceptance — owner

Salma Al-Zaim

Approved⁦2025-08-31⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2025-09-01⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2025-09-03⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2025-08-26⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-08-28⁩ at ⁦14:47⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-08-31⁩ at ⁦09:54⁩ · On behalf of Eng. Wassim Al-Azm (Salma Al-Zaim)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-01⁩ at ⁦09:24⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-03⁩ at ⁦10:01⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-08-26⁩

    PRJ-2026-036_3.2_v1.pdf

    Eng. Maher Al-Hamawi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close