PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-12-08⁩
ApprovedDMD-2026-034Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-034
Project
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Eng. Wael Al-Khawlani

1The proposalAuto-filled

TitleAuto-filled
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Proposed byAuto-filled
Eng. Wael Al-Khawlani
DepartmentAuto-filled
Transport & Housing Projects Directorate
Submitted onAuto-filled
⁦2024-12-08⁩
Proposal numberAuto-filled
DMD-2026-034

2Justification

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

3Objectives

  1. Rebuild damaged areas and provide replacement housing
  2. Comparable public-service quality in every governorate

Strategic objectives served

  • SO-2.2 — Rebuild damaged areas and provide replacement housing
  • SO-6.1 — Comparable public-service quality in every governorate

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 6B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 4.3B
Supervision & consultingSYP 832.5M
Internal teamSYP 535M
Contingency reserve (5%)SYP 297.5M
TotalSYP 6B

6Initial risks

RiskLevelProposed response
City council late clearing rubble and opening access roads to the work sitesHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsSubmitted—⁦2024-12-08⁩ 09:36
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-12-09⁩ 13:16
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-12-12⁩ 14:23
4Portfolio manager reviewTechnical acceptanceEng. Wassim Al-AzmPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-12-15⁩ 09:30
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-12-16⁩ 09:12
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-12-19⁩ 11:44

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-12-09⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-12-12⁩

Portfolio manager review

Eng. Wassim Al-Azm

Approved⁦2024-12-15⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-12-16⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-12-19⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Wael Al-Khawlani on ⁦2024-12-08⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-12-09⁩ at ⁦13:16⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-12-12⁩ at ⁦14:23⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Wassim Al-Azm · Portfolio manager

    Approved · ⁦2024-12-15⁩ at ⁦09:30⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-12-16⁩ at ⁦09:12⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-12-19⁩ at ⁦11:44⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-12-29⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Wael Al-Khawlani

  2. V1Returned for edit⁦2024-12-08⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Wael Al-Khawlani