PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

PRJ-2026-034 · Development Projects Follow-up Sector · External · WP-2025-034

In progressAt risk4ExecutionProject manager: Eng. Wael Al-Khawlani · Sponsor: Eng. Abdulrahman Al-Kilani
Progress
⁦33%⁩ / ⁦37%⁩
SPI · CPI
0.89 · 0.96
Spend
SYP 2B / SYP 6B
Estimate at completion
SYP 6.2B

Schedule

⁦4%⁩ behind⁦33%⁩

Planned to date ⁦37%⁩

Forecast finish: 2027-09-28 · 28 days late

SPI0.89Schedule performance index · 0.89CPI0.96Cost performance index · 0.96

Health dimensions

At risk

Last update: 2026-09-02 · Update overdue

Deliverables

⁦4⁩ of ⁦7⁩ due deliverables accepted on time (⁦57%⁩)

Next milestones

  • Build complete2027-03-01
  • Testing & acceptance complete2027-07-05
  • Final handover2027-09-27

Top risks

  • City council late clearing rubble and opening access roads to the work sites16

Open impediments

  • Monthly progress reports incomplete · Overdue

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 5.95bn: 0 on track and 0 red or critical. Weighted progress is 33% against 37% planned, spend SYP 2.05bn, and EAC SYP 6.2bn (SYP 247.9M over).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. Wael Al-Khawlani in MunjazInternal

Status: At risk ·Project page