Project status card
28 October 2026
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
PRJ-2026-034 · Development Projects Follow-up Sector · External · WP-2025-034
- Progress
- 33% / 37%
- SPI · CPI
- 0.89 · 0.96
- Spend
- SYP 2B / SYP 6B
- Estimate at completion
- SYP 6.2B
Schedule
Planned to date 37%
Forecast finish: 2027-09-28 · 28 days late
SPI0.89Schedule performance index · 0.89CPI0.96Cost performance index · 0.96Health dimensions
Last update: 2026-09-02 · Update overdue
Deliverables
4 of 7 due deliverables accepted on time (57%)
Next milestones
- Build complete2027-03-01
- Testing & acceptance complete2027-07-05
- Final handover2027-09-27
Top risks
- City council late clearing rubble and opening access roads to the work sites16
Open impediments
- Monthly progress reports incomplete · Overdue
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 5.95bn: 0 on track and 0 red or critical. Weighted progress is 33% against 37% planned, spend SYP 2.05bn, and EAC SYP 6.2bn (SYP 247.9M over).
No project is more than a month behind baseline.