PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-08-27⁩
In approvalPRJ-2026-022Population & Housing Census Preparation — Phase 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-022
Project
Population & Housing Census Preparation — Phase 1
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Statistics Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Ayman Sabbagh

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-08-02⁩

Baseline finish

⁦2028-03-31⁩

Forecast finish

⁦2028-03-31⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2026-12-05⁩⁦2027-01-08⁩+34 days
Designs approved⁦2027-03-12⁩⁦2027-04-08⁩+27 days
Build complete⁦2027-08-03⁩⁦2027-08-21⁩+18 days
Testing & acceptance complete⁦2027-12-26⁩⁦2028-01-03⁩+8 days
Final handover⁦2028-03-31⁩⁦2028-04-02⁩+2 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦2%⁩⁦2026-10-18⁩Ayman Sabbagh
Monitoring & reporting⁦3%⁩⁦2026-12-05⁩Dr. Firas Al-Obaid
Detailed design⁦6%⁩⁦2027-01-22⁩Dr. Firas Al-Obaid
Permits & approvals⁦6%⁩⁦2027-03-12⁩Eng. Khaled Al-Kayyali
Site works & excavation⁦13%⁩⁦2027-04-29⁩Eng. Khaled Al-Kayyali
Structure⁦13%⁩⁦2027-06-16⁩Ayman Sabbagh
Finishes⁦13%⁩⁦2027-08-03⁩Dr. Firas Al-Obaid
Supply⁦10%⁩⁦2027-09-20⁩Ayman Sabbagh
Installation⁦10%⁩⁦2027-11-07⁩Dr. Firas Al-Obaid
Testing & commissioning⁦10%⁩⁦2027-12-26⁩Eng. Khaled Al-Kayyali
Provisional acceptance⁦7%⁩⁦2028-02-12⁩Dr. Firas Al-Obaid
Final acceptance⁦7%⁩⁦2028-03-31⁩Eng. Khaled Al-Kayyali
Accepted with a certificate⁦2%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0047Confidentiality of individual census data under the statistics law9MitigateEng. Hussam Zeidan

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyAyman Sabbagh
Project ownerDeliverable status and acceptance datesFortnightlyAyman Sabbagh
PMOData and indicator updatesWeeklyAyman Sabbagh
BeneficiariesWhat changes and whenAt each milestoneAyman Sabbagh
Team memberRoleAllocation
Ayman SabbaghProject manager⁦25%⁩
Eng. Tarek Al-MardiniAdviser on linking the census field forms to the unified platform channels⁦15%⁩
Eng. Hussam ZeidanCybersecurity for the census field tablets and data⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ayman SabbaghCensus & National Development Forum ConsultantSubmitted—⁦2026-10-23⁩ 14:17
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-10-26⁩ 10:19

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2026-10-26⁩

Technical acceptance — project owner

Dr. Firas Al-Obaid

Awaiting decision

Cash flow & financial commitment

Rasha Al-Mudarres

Later

Sponsor approval

Eng. Khaled Al-Kayyali

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Ayman Sabbagh on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-10-26⁩ at ⁦10:19⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Dr. Firas Al-Obaid · Project owner
    1 working day leftWithin the time limit · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-29⁩
    Waiting on Dr. Firas Al-Obaid
  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    Limit 2 working days · Expected by ⁦2026-11-02⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Delegated to Dr. Reem Al-Qabbani

    Limit 3 working days · Expected by ⁦2026-11-05⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-08-27⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Ayman Sabbagh

  2. V1Returned for editCurrent⁦2026-08-13⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Ayman Sabbagh