Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 1.2B split into spent, committed and left, with the estimate at completion

EAC SYP 1.2B
Revised request SYP 1.2B
  • Actual spendSYP 23M
  • Committed, not spentSYP 4.5M
  • Allotted, uncommittedSYP 1.1B
  • Contingency availableSYP 34.5M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 1.2B
Original budgetwhen the first baseline was approved
SYP 1.2B
Approved budgetafter approved change requests
SYP 1.2B
Current budgetavailable to spend now
SYP 1.2B
Revised budgetif the pending changes are approved
SYP 1.2B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 27.5M
Contracts0 active contracts
SYP 0
Purchase orders⁦2⁩ orders
SYP 27.5M
Remaining budgetapproved less actual
SYP 1.1B

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 23M
Accrualswork done, not yet invoiced
SYP 920K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 1.2B
ContingencySYP 23M drawn of SYP 57.5M
SYP 34.5M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 1.2B
ApprovedSYP 1.2B
Estimate at completionSYP 1.2B
Approved is SYP 12.5M (⁦1.1%⁩) below the estimate
The estimate at completion is SYP 12.5M (⁦1.1%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2026-05-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-90022
  • WBS elements⁦5⁩ elements · P-2026-022.01 …
  • Purchase orders⁦1⁩ synced · ⁦1⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 23M drawn of SYP 57.5M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 23M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance66.9323.1823.0067.62⁦−0.69⁩
2Design & permits133.860.550.00135.97⁦−2.11⁩
3Civil works423.891.750.00430.58⁦−6.69⁩
4MEP works334.651.380.00339.93⁦−5.28⁩
5Handover156.170.640.00158.64⁦−2.47⁩
Unallocated contingency34.500.000.0017.25⁦+17.25⁩
Total1,150.0027.5023.001,150.00⁦+0.00⁩

Budget split

WBS

SYP 1.2B

Budget

  • Management & governanceSYP 66.9M⁦6%⁩
  • Design & permitsSYP 133.9M⁦12%⁩
  • Civil worksSYP 423.9M⁦37%⁩
  • MEP worksSYP 334.7M⁦29%⁩
  • HandoverSYP 156.2M⁦14%⁩
  • Unallocated contingencySYP 34.5M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-09-03⁩+521

SPI(t) ⁦0.54⁩ against the approved finish ⁦2028-03-31⁩

Planned valuePV
SYP 69.9M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 23M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 23M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 1.2B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−46.86⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.33
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 1.2B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 1.1B
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 1.2B
  • If the rest goes to planSYP 1.2B
  • At cost and schedule performanceSYP 3.4B
  • The PM’s bottom-up estimateSYP 1.2B
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 1.2B

Variance at completion: ⁦+0.00⁩ SYP M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close