PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Population & Housing Census Preparation — Phase 1

APPROVEDV2Approved ⁦2026-07-31⁩

1Project identity

Required at this stage
Project name
Population & Housing Census Preparation — Phase 1
Project code
PRJ-2026-022
Project sponsor
Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy
Project manager
Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy
Project owner
Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy
Portfolio & programme
Reconstruction & Infrastructure PortfolioNational Connectivity & Support Services Programme
Type & methodology
Infrastructure · Stage-Gate
Current phase
3Planning

2Background & rationale

Required at this stage

⁦Phase 1 of the census preparation⁩: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

3Objectives

Required at this stage
  1. 1Reliable statistics and economic data for decisions
  2. 2Governorate plans and a balanced share of public investment

4Scope

Required at this stage

In scope

  • ⁦Phase 1 of the census preparation⁩: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2026-08-26⁩
2Main deliverable — stage 1⁦2027-06-08⁩
3Main deliverable — final stage⁦2028-01-06⁩
4Final report⁦2028-03-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-07-31⁩
  2. Contract signed⁦2026-11-07⁩
  3. 50% of works complete⁦2027-06-08⁩
  4. Provisional acceptance⁦2028-02-11⁩
  5. Closure⁦2028-03-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP827.5M
  • Supervision & consulting⁦14.1%⁩SYP162.5M
  • Internal team⁦8.9%⁩SYP102.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP57.5M
The delivering body’s investment-plan allocationsTotalSYP1.2B

9Timeline

Required at this stage
Start
2026-08-022 August 2026
Baseline finish
2028-03-3131 March 2028
Duration
⁦20⁩ months

10Key risks

Required at this stage
  • MediumConfidentiality of individual census data under the statistics law

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly