Population & Housing Census Preparation — Phase 1
Add to watchlistPhase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution7 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2028-03-31
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Dr. Firas Al-ObaidPlanned 2028-03-21
- 2
Financial closureNot started
Spend reconciled, commitments closed
Omar Al-NahhasPlanned 2028-04-20
- 3
Contract closureNot started
Contracts closed, bonds released
Omar Al-NahhasPlanned 2028-04-30
- 4
Documents archivedNot started
Documents archived with classification
Ayman SabbaghPlanned 2028-04-25
- 5
Lessons learnedNot started
Lessons-learned session
Ayman SabbaghPlanned 2028-04-15
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Dr. Firas Al-ObaidPlanned 2028-04-10
- 7
Final report approvedNot started
Final report and its approval
Ayman SabbaghPlanned 2028-05-05
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2028-03-31), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.