PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
3On track
2At risk
0Late
Average delay18 days
Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28
Contractual
Build completePlanned: ⁦2027-08-03⁩Forecast / actual: ⁦2027-08-21⁩Delay: 18 daysG3 +18
Executive
Project plan approvedPlanned: ⁦2026-12-05⁩Forecast / actual: ⁦2027-01-08⁩Delay: 34 daysG1 +34
Payment
Final handoverPlanned: ⁦2028-03-31⁩Forecast / actual: ⁦2028-04-02⁩Delay: 2 daysG5 +2
Regulatory
Testing & acceptance completePlanned: ⁦2027-12-26⁩Forecast / actual: ⁦2028-01-03⁩Delay: 8 daysG4 +8
Project
Designs approvedPlanned: ⁦2027-03-12⁩Forecast / actual: ⁦2027-04-08⁩Delay: 27 daysG2 +27

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-12-05⁩⁦2027-01-08⁩⁦+34⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Designs approvedMS-G2Project⁦2027-03-12⁩⁦2027-04-08⁩⁦+27⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Build completeMS-G3Contractual⁦2027-08-03⁩⁦2027-08-21⁩⁦+18⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syOn track0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-12-26⁩⁦2028-01-03⁩⁦+8⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syOn track0Not requested
Final handoverMS-G5Payment⁦2028-03-31⁩⁦2028-04-02⁩⁦+2⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦2%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦98%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline022-D1⁦2%⁩CRT-022-01ApprovedAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syDr. Firas Al-Obaid⁦2026-10-18⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting022-D2⁦3%⁩—DraftDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.syDr. Firas Al-Obaid⁦2026-12-05⁩V0⁦0⁩ of ⁦3⁩
Detailed design022-D3⁦6%⁩—DraftDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.syDr. Firas Al-Obaid⁦2027-01-22⁩V0⁦0⁩ of ⁦3⁩
Permits & approvals022-D4⁦6%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syDr. Firas Al-Obaid⁦2027-03-12⁩V0⁦0⁩ of ⁦3⁩
Site works & excavation022-D5⁦13%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syDr. Firas Al-Obaid⁦2027-04-29⁩V0⁦0⁩ of ⁦3⁩
Structure022-D6⁦13%⁩—DraftAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syDr. Firas Al-Obaid⁦2027-06-16⁩V0⁦0⁩ of ⁦3⁩
Finishes022-D7⁦13%⁩—DraftDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.syDr. Firas Al-Obaid⁦2027-08-03⁩V0⁦0⁩ of ⁦3⁩
Supply022-D8⁦10%⁩—DraftAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syDr. Firas Al-Obaid⁦2027-09-20⁩V0⁦0⁩ of ⁦3⁩
Installation022-D9⁦10%⁩—DraftDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.syDr. Firas Al-Obaid⁦2027-11-07⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning022-D10⁦10%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syDr. Firas Al-Obaid⁦2027-12-26⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance022-D11⁦7%⁩—DraftDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.syDr. Firas Al-Obaid⁦2028-02-12⁩V0⁦0⁩ of ⁦3⁩
Final acceptance022-D12⁦7%⁩—DraftEng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.syDr. Firas Al-Obaid⁦2028-03-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩