Population & Housing Census Preparation — Phase 1
Add to watchlistPhase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution7 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-05 | 2027-01-08 | +34 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-12 | 2027-04-08 | +27 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-08-03 | 2027-08-21 | +18 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-12-26 | 2028-01-03 | +8 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-03-31 | 2028-04-02 | +2 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline022-D1 | 2% | CRT-022-01 | Approved | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Dr. Firas Al-Obaid | 2026-10-18 | V1 | 3 of 3 |
| Monitoring & reporting022-D2 | 3% | — | Draft | Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy | Dr. Firas Al-Obaid | 2026-12-05 | V0 | 0 of 3 |
| Detailed design022-D3 | 6% | — | Draft | Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy | Dr. Firas Al-Obaid | 2027-01-22 | V0 | 0 of 3 |
| Permits & approvals022-D4 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Dr. Firas Al-Obaid | 2027-03-12 | V0 | 0 of 3 |
| Site works & excavation022-D5 | 13% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Dr. Firas Al-Obaid | 2027-04-29 | V0 | 0 of 3 |
| Structure022-D6 | 13% | — | Draft | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Dr. Firas Al-Obaid | 2027-06-16 | V0 | 0 of 3 |
| Finishes022-D7 | 13% | — | Draft | Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy | Dr. Firas Al-Obaid | 2027-08-03 | V0 | 0 of 3 |
| Supply022-D8 | 10% | — | Draft | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Dr. Firas Al-Obaid | 2027-09-20 | V0 | 0 of 3 |
| Installation022-D9 | 10% | — | Draft | Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy | Dr. Firas Al-Obaid | 2027-11-07 | V0 | 0 of 3 |
| Testing & commissioning022-D10 | 10% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Dr. Firas Al-Obaid | 2027-12-26 | V0 | 0 of 3 |
| Provisional acceptance022-D11 | 7% | — | Draft | Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy | Dr. Firas Al-Obaid | 2028-02-12 | V0 | 0 of 3 |
| Final acceptance022-D12 | 7% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Dr. Firas Al-Obaid | 2028-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |