PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

⁦Phase 1 of the census preparation⁩: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

In scope

  • ⁦Phase 1 of the census preparation⁩: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2026-08-31⁩

    Baseline approved at the planning gate

    BudgetSYP1.2BFinish⁦2028-03-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦0%⁩

0/6 · linked to a deliverable, task and test

Test passed

⁦0%⁩

0/6 · test result is a pass

Accepted

⁦0%⁩

0/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-022-01Reach the target capacity of rehabilitated facilitiesBusinessMustApprovedDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sySB-1
REQ-022-02Meet the approved technical specsTechnicalMustApprovedAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sySB-1
REQ-022-03Services to residents continue during the worksFunctionalMustApprovedDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sySB-1
REQ-022-04Syrian Arab Building CodeRegulatoryShouldApprovedAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sySB-1
REQ-022-05Civil-defence requirementsRegulatoryCouldApprovedDr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sySB-1
REQ-022-06Site and systems securitySecurityCouldApprovedAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sySB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired from Execution

Requirement → deliverable → task → test → acceptance. ⁦6⁩ requirements have a gap.