MunjazStrategy & projectsMunjazPMO PLATFORMPlanning and Statistics Authority
PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology
Unified Government e-Services Platform
Remove from watchlist
One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.
Early warning: 74% chance of slipping within 45 days
Budget (BAC)
SYP 2.2B
Actual cost
SYP 1.3B
60% of budget
Progress
58%Awaiting acceptance 23%
Estimate at completion
SYP 2.3B
+SYP 90M
SPI · CPI
0.87Schedule performance index · 0.870.96Cost performance index · 0.96
Forecast finish
2027-05-12
42 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure31 March 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Public financial management system integrationPlanned: 2026-06-01 → 2026-12-31Forecast: 2026-06-15 → 2027-01-31Float: 101dDrag to change its duration+31
2026-12-100%
Civil-registry & interoperability integration completePlanned: 2026-10-31 → 2026-10-31Forecast: 2026-12-10 → 2026-12-10Float: 0dDrag to change its datesCivil-registry & interoperability integration complete
2027-02-1045%
Data migrationPlanned: 2026-04-01 → 2026-12-31Forecast: 2026-04-01 → 2027-02-10Float: 91d
2026-11-3070%
Transaction & beneficiary data profiling & cleansingPlanned: 2026-04-01 → 2026-10-31Forecast: 2026-04-01 → 2026-11-30Float: 113dDrag to change its duration+30
2026-07-14100%
Data classification approved under the policyPlanned: 2026-06-30 → 2026-06-30Actual: 2026-07-14 → 2026-07-14Data classification approved under the policy
2027-02-1020%
Open transaction records migration & reconciliationPlanned: 2026-09-01 → 2026-12-31Forecast: 2026-09-20 → 2027-02-10Float: 91dDrag to change its duration+41
Computed from the current plan: 34 open activities, data date 2026-10-28
Recommendation72% confidence
Approving CR-2026-012 wins back 12 days
Extra vendor integration capacity shortens the two critical civil-registry and interoperability activities, pulling launch and final acceptance forward.