PRJ-2026-012On track4ExecutionAgileIn progressDelivered by:Planning and Statistics Authority

Ministries Performance Follow-up & National Dashboards

Add to watchlist

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

Budget (BAC)

SYP 245M

Actual cost

SYP 186.2M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SYP 245M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 245M split into spent, committed and left, with the estimate at completion

EAC SYP 245M
Revised request SYP 245M
  • Actual spendSYP 186.2M
  • Committed, not spentSYP 28.8M
  • Allotted, uncommittedSYP 22.7M
  • Contingency availableSYP 7.4M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 215M
Original budgetwhen the first baseline was approved
SYP 245M
Approved budgetafter approved change requests
SYP 245M
Current budgetavailable to spend now
SYP 245M
Revised budgetif the pending changes are approved
SYP 245M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 215M
Contracts0 active contracts
SYP 0
Purchase orders⁦3⁩ orders
SYP 215M
Remaining budgetapproved less actual
SYP 58.8M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 186.2M
Accrualswork done, not yet invoiced
SYP 7.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 245M
ContingencySYP 4.9M drawn of SYP 12.3M
SYP 7.4M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 215M
ApprovedSYP 245M
Estimate at completionSYP 245M
Approved is SYP 30M (⁦14.0%⁩) above the estimate
The estimate at completion is SYP 30M (⁦14.0%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-06-24⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-21012
  • WBS elements⁦5⁩ elements · P-2026-012.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 4.9M drawn of SYP 12.3M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 4.9M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance23.7724.4824.4824.48⁦−0.72⁩
2Diagnosis47.5348.9748.9748.97⁦−1.44⁩
3Design71.3073.4573.4573.45⁦−2.16⁩
4Implementation71.3055.8239.3070.93⁦+0.37⁩
5Handover & knowledge transfer23.7712.270.0023.49⁦+0.27⁩
Unallocated contingency7.350.000.003.68⁦+3.68⁩
Total245.00215.00186.20245.00⁦+0.00⁩

Budget split

WBS

SYP 245M

Budget

  • Management & governanceSYP 23.8M⁦10%⁩
  • DiagnosisSYP 47.5M⁦19%⁩
  • DesignSYP 71.3M⁦29%⁩
  • ImplementationSYP 71.3M⁦29%⁩
  • Handover & knowledge transferSYP 23.8M⁦10%⁩
  • Unallocated contingencySYP 7.4M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-05-16⁩+136

SPI(t) ⁦0.78⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SYP 234.5M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 186.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 186.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 245M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−48.27⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.79
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 245M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 58.8M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 245M
  • If the rest goes to planSYP 245M
  • At cost and schedule performanceSYP 260.2M
  • The PM’s bottom-up estimateSYP 245M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 245M

Variance at completion: ⁦+0.00⁩ SYP M