PRJ-2026-012On track4ExecutionAgileIn progressDelivered by:Planning and Statistics Authority

Ministries Performance Follow-up & National Dashboards

Add to watchlist

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

Budget (BAC)

SYP 245M

Actual cost

SYP 186.2M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SYP 245M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Ministries Performance Follow-up & National Dashboards

APPROVEDV2Approved ⁦2025-09-05⁩

1Project identity

Required at this stage
Project name
Ministries Performance Follow-up & National Dashboards
Project code
PRJ-2026-012
Project sponsor
Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy
Project manager
Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy
Project owner
Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy
Portfolio & programme
Planning, Statistics & Capability PortfolioPlanning, Statistics & Capability Programme
Type & methodology
Transformation · Agile
Current phase
4Execution

2Background & rationale

Required at this stage

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

3Objectives

Required at this stage
  1. 1Sound governance and effective follow-up of projects and data

4Scope

Required at this stage

In scope

  • Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1As-is and to-be analysis
  2. 2Change management plan
  3. 3Adoption measures

6Deliverables

Required at this stage
1Project management plan⁦2025-09-26⁩
2Main deliverable — stage 1⁦2026-05-10⁩
3Main deliverable — final stage⁦2026-10-25⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-09-05⁩
  2. Contract signed⁦2025-11-23⁩
  3. 50% of works complete⁦2026-05-10⁩
  4. Provisional acceptance⁦2026-11-23⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.4%⁩SYP177.5M
  • Supervision & consulting⁦13.3%⁩SYP32.5M
  • Internal team⁦9.2%⁩SYP22.5M
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩SYP12.5M
The delivering body’s investment-plan allocationsTotalSYP245M

9Timeline

Required at this stage
Start
2025-09-077 September 2025
Baseline finish
2026-12-3131 December 2026
Duration
⁦16⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly