Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SYP 245M
- 15 activities
Approved with the project plan at the planning gate.
Approved 2025-09-07 · by Dr. Ziad Al-Atassi
Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.
Budget (BAC)
Actual cost
76% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-09-07 · by Dr. Ziad Al-Atassi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Nizar Abu Fakhr
What changed from version A to version B
Finish
2026-12-312027-01-23
+23 days
Budget
SYP 245MSYP 245M
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference