Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-012On track4ExecutionAgileIn progressDelivered by:Planning and Statistics Authority

Ministries Performance Follow-up & National Dashboards

Add to watchlist

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

Budget (BAC)

SYP 245M

Actual cost

SYP 186.2M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SYP 245M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP237.7M⁦15⁩ elements
Unallocated contingencySYP7.4MSYP 12.3M
Budget at completionSYP245MPRJ-2026-012
Weighted progress⁦76%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project503⁦2025-09-07⁩⁦2027-01-23⁩⁦76%⁩237.65186.20—
1
Phase142⁦2025-09-07⁩⁦2026-01-27⁩⁦100%⁩23.7724.48—
1.1
WBS element88⁦2025-09-07⁩⁦2025-12-04⁩⁦100%⁩11.8812.240 / 1
1.2
WBS element87⁦2025-11-01⁩⁦2026-01-27⁩⁦100%⁩11.8812.241 / 2
2
Phase142⁦2025-12-26⁩⁦2026-05-17⁩⁦100%⁩47.5348.97—
2.1
WBS element87⁦2025-12-26⁩⁦2026-03-23⁩⁦100%⁩23.7724.481 / 1
2.2
WBS element88⁦2026-02-18⁩⁦2026-05-17⁩⁦100%⁩23.7724.481 / 2
3
Phase142⁦2026-04-14⁩⁦2026-09-03⁩⁦100%⁩71.3073.45—
3.1
WBS element88⁦2026-04-14⁩⁦2026-07-11⁩⁦100%⁩35.6536.731 / 1
3.2
WBS element87⁦2026-06-08⁩⁦2026-09-03⁩⁦100%⁩35.6536.731 / 2
4
Phase166⁦2026-07-21⁩⁦2027-01-03⁩⁦54%⁩71.3039.30—
4.1
WBS element85⁦2026-08-02⁩⁦2026-10-26⁩⁦100%⁩35.6536.731 / 1
4.2
WBS element166⁦2026-07-21⁩⁦2027-01-03⁩⁦7%⁩35.652.571 / 2
5
Phase26⁦2026-12-28⁩⁦2027-01-23⁩⁦0%⁩23.77——
5.1
WBS element16⁦2026-12-28⁩⁦2027-01-13⁩⁦0%⁩11.88—1 / 1
5.2
WBS element16⁦2027-01-07⁩⁦2027-01-23⁩⁦0%⁩11.88—1 / 1
Total⁦76%⁩237.65186.20
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close