20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
1On track
1At risk
0Late
Average delay64 days
Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2026-06-21⁩Forecast / actual: ⁦2026-10-26⁩Delay: 127 daysG3 +127
Executive
Project plan approvedPlanned: ⁦2025-08-12⁩Forecast / actual: ⁦2025-09-25⁩Delay: 44 daysG1 +44
Payment
Final handoverPlanned: ⁦2027-04-30⁩Forecast / actual: ⁦2027-04-30⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-12-26⁩Forecast / actual: ⁦2027-03-05⁩Delay: 69 daysG4 +69
Project
Designs approvedPlanned: ⁦2025-12-15⁩Forecast / actual: ⁦2026-03-03⁩Delay: 78 daysG2 +78

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-08-12⁩⁦2025-09-25⁩⁦+44⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-15⁩⁦2026-03-03⁩⁦+78⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-06-21⁩⁦2026-10-26⁩⁦+127⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-12-26⁩⁦2027-03-05⁩⁦+69⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-04-30⁩⁦2027-04-30⁩On timeEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦58%⁩

Awaiting acceptance

⁦10%⁩

Not handed in

⁦32%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline010-D1⁦3%⁩CRT-010-01ApprovedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2025-06-10⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting010-D2⁦3%⁩CRT-010-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-08-12⁩V1⁦3⁩ of ⁦3⁩
Detailed design010-D3⁦7%⁩CRT-010-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-10-13⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals010-D4⁦6%⁩CRT-010-04ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-12-15⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation010-D5⁦13%⁩CRT-010-05ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-02-16⁩V1⁦3⁩ of ⁦3⁩
Structure010-D6⁦13%⁩CRT-010-06ApprovedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2026-04-19⁩V1⁦3⁩ of ⁦3⁩
Finishes010-D7⁦13%⁩CRT-010-07ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-06-21⁩V1⁦3⁩ of ⁦3⁩
Supply010-D8⁦10%⁩—SubmittedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2026-08-23⁩V1⁦1⁩ of ⁦3⁩
Installation010-D9⁦9%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-10-24⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning010-D10⁦9%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-12-26⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance010-D11⁦7%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-02-26⁩V0⁦0⁩ of ⁦3⁩
Final acceptance010-D12⁦7%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2027-04-30⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩