Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
PSA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
ApprovedPRJ-2026-01020 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1Weight and relative weightAuto-filled

Project weight score

71 of 100

Relative weight in the portfolio

⁦20.9%⁩

Portfolio

Energy & Water Portfolio

5 projects

Its share of the portfolio’s progress

12.1 points of 54.9%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩315.0
Impact on citizens & beneficiariesThe project’s alignment score⁦20%⁩520.0
Complexity & riskThe project’s risk score⁦10%⁩24.0
Project classificationThe project’s classification⁦10%⁩24.0
Weight score—⁦100%⁩—71

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Aleppo 230 kV Substations Rehabilitation83⁦24.4%⁩⁦68%⁩
20 MW Qalamoun Solar Field71⁦20.9%⁩⁦58%⁩
Madinat al-Salam Drinking-Water Network (Quneitra)65⁦19.1%⁩⁦97%⁩
Suwayda Drinking-Water Network from Al-Ain Dam62⁦18.2%⁩⁦36%⁩
Baniyas Pilot Seawater Desalination Plant59⁦17.4%⁩⁦6%⁩
Weighted portfolio progress—⁦100%⁩⁦54.9%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-09-16⁩ 09:36
2Weight model complianceMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-17⁩ 11:20
3Portfolio manager approvalTechnical acceptanceEng. Rami YoussefPortfolio managerApproved—⁦2026-09-20⁩ 12:27

Signatures

Weight model compliance

Mariam Al-Zoubi

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Rami Youssef

Approved⁦2026-09-20⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦11:20⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2026-09-20⁩ at ⁦12:27⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Reem Al-Qabbani

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Reem Al-Qabbani