PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
0On track
1At risk
0Late
Average delay33 days
Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-01-04⁩Forecast / actual: ⁦2026-02-11⁩Delay: 38 daysG3 +38
Executive
Project plan approvedPlanned: ⁦2025-03-11⁩Forecast / actual: ⁦2025-03-24⁩Delay: 13 daysG1 +13
Payment
Final handoverPlanned: ⁦2026-10-31⁩Forecast / actual: ⁦2026-12-08⁩Delay: 38 daysG5 +38
Regulatory
Testing & acceptance completePlanned: ⁦2026-07-03⁩Forecast / actual: ⁦2026-08-24⁩Delay: 52 daysG4 +52
Project
Designs approvedPlanned: ⁦2025-07-09⁩Forecast / actual: ⁦2025-07-31⁩Delay: 22 daysG2 +22

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-03-11⁩⁦2025-03-24⁩⁦+13⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-07-09⁩⁦2025-07-31⁩⁦+22⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-01-04⁩⁦2026-02-11⁩⁦+38⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-07-03⁩⁦2026-08-24⁩⁦+52⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Final handoverMS-G5Payment⁦2026-10-31⁩⁦2026-12-08⁩⁦+38⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦97%⁩

Awaiting acceptance

⁦3%⁩

Not handed in

⁦0%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline036-D1⁦3%⁩CRT-036-01ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2025-01-10⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting036-D2⁦3%⁩CRT-036-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-03-11⁩V1⁦3⁩ of ⁦3⁩
Detailed design036-D3⁦6%⁩CRT-036-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-05-10⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals036-D4⁦6%⁩CRT-036-04ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-07-09⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation036-D5⁦13%⁩CRT-036-05ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-09-07⁩V1⁦3⁩ of ⁦3⁩
Structure036-D6⁦13%⁩CRT-036-06ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2025-11-05⁩V1⁦3⁩ of ⁦3⁩
Finishes036-D7⁦13%⁩CRT-036-07ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-01-04⁩V1⁦3⁩ of ⁦3⁩
Supply036-D8⁦11%⁩CRT-036-08ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2026-03-05⁩V1⁦3⁩ of ⁦3⁩
Installation036-D9⁦11%⁩CRT-036-09ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-05-04⁩V1⁦3⁩ of ⁦3⁩
Testing & commissioning036-D10⁦11%⁩CRT-036-10ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-07-03⁩V1⁦3⁩ of ⁦3⁩
Provisional acceptance036-D11⁦7%⁩CRT-036-11ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-09-01⁩V1⁦3⁩ of ⁦3⁩
Final acceptance036-D12⁦3%⁩—SubmittedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-10-31⁩V1⁦1⁩ of ⁦3⁩
Total · 12⁦100%⁩