PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay78 days
Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-10-23⁩Forecast / actual: ⁦2027-03-01⁩Delay: 129 daysG3 +129
Executive
Project plan approvedPlanned: ⁦2025-12-15⁩Forecast / actual: ⁦2026-02-14⁩Delay: 61 daysG1 +61
Payment
Final handoverPlanned: ⁦2027-08-31⁩Forecast / actual: ⁦2027-09-27⁩Delay: 27 daysG5 +27
Regulatory
Testing & acceptance completePlanned: ⁦2027-04-28⁩Forecast / actual: ⁦2027-07-05⁩Delay: 68 daysG4 +68
Project
Designs approvedPlanned: ⁦2026-04-19⁩Forecast / actual: ⁦2026-08-04⁩Delay: 107 daysG2 +107

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-12-15⁩⁦2026-02-14⁩⁦+61⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-19⁩⁦2026-08-04⁩⁦+107⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-10-23⁩⁦2027-03-01⁩⁦+129⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-04-28⁩⁦2027-07-05⁩⁦+68⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-08-31⁩⁦2027-09-27⁩⁦+27⁩ daysEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦33%⁩

Awaiting acceptance

⁦12%⁩

Not handed in

⁦55%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline034-D1⁦3%⁩CRT-034-01ApprovedEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Fadi Al-Droubi⁦2025-10-14⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting034-D2⁦3%⁩CRT-034-02ApprovedEng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.syEng. Fadi Al-Droubi⁦2025-12-15⁩V1⁦3⁩ of ⁦3⁩
Detailed design034-D3⁦7%⁩CRT-034-03ApprovedEng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.syEng. Fadi Al-Droubi⁦2026-02-16⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals034-D4⁦6%⁩CRT-034-04ApprovedEng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.syEng. Fadi Al-Droubi⁦2026-04-19⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation034-D5⁦14%⁩CRT-034-05ApprovedEng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.syEng. Fadi Al-Droubi⁦2026-06-20⁩V1⁦3⁩ of ⁦3⁩
Structure034-D6⁦12%⁩—SubmittedEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Fadi Al-Droubi⁦2026-08-22⁩V1⁦1⁩ of ⁦3⁩
Finishes034-D7⁦12%⁩—DraftEng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.syEng. Fadi Al-Droubi⁦2026-10-23⁩V0⁦0⁩ of ⁦3⁩
Supply034-D8⁦10%⁩—DraftEng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syEng. Fadi Al-Droubi⁦2026-12-24⁩V0⁦0⁩ of ⁦3⁩
Installation034-D9⁦10%⁩—DraftEng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.syEng. Fadi Al-Droubi⁦2027-02-25⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning034-D10⁦9%⁩—DraftEng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.syEng. Fadi Al-Droubi⁦2027-04-28⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance034-D11⁦7%⁩—DraftEng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.syEng. Fadi Al-Droubi⁦2027-06-30⁩V0⁦0⁩ of ⁦3⁩
Final acceptance034-D12⁦7%⁩—DraftEng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.syEng. Fadi Al-Droubi⁦2027-08-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩