PRJ-2026-028On track4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Add to watchlist

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

Budget (BAC)

SYP 80M

Actual cost

SYP 56M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 80M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-10-05⁩
ApprovedDMD-2026-028Preparing the 2026–2028 Medium-Term Plan & Governorate Plans

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
Preparing the 2026–2028 Medium-Term Plan & Governorate Plans
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Rana Al-Samman

1The proposalAuto-filled

TitleAuto-filled
Preparing the 2026–2028 Medium-Term Plan & Governorate Plans
Proposed byAuto-filled
Rana Al-Samman
DepartmentAuto-filled
National Strategy Directorate
Submitted onAuto-filled
⁦2025-10-05⁩
Proposal numberAuto-filled
DMD-2026-028

2Justification

Preparing the 2026–2028 medium-term plan in place of the five-year plans, development plans for the 14 governorates and scorecards that tie projects to the framework’s pillars.

3Objectives

  1. Governorate plans and a balanced share of public investment
  2. Reliable statistics and economic data for decisions

Strategic objectives served

  • SO-6.2 — Governorate plans and a balanced share of public investment
  • SO-1.2 — Reliable statistics and economic data for decisions

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 80M

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 57.5M
Supervision & consultingSYP 10M
Internal teamSYP 7.5M
Contingency reserve (5%)SYP 5M
TotalSYP 80M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rana Al-SammanHead of National StrategySubmitted—⁦2025-10-05⁩ 12:27
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2025-10-07⁩ 10:37
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-10-12⁩ 11:44
4Portfolio manager reviewTechnical acceptanceDr. Reem Al-QabbaniPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-10-13⁩ 12:51
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-10-15⁩ 12:03
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-10-16⁩ 14:05

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2025-10-07⁩

PMO review

Mariam Al-Zoubi

Approved⁦2025-10-12⁩

Portfolio manager review

Dr. Reem Al-Qabbani

Approved⁦2025-10-13⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2025-10-15⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-10-16⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Rana Al-Samman on ⁦2025-10-05⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2025-10-07⁩ at ⁦10:37⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-10-12⁩ at ⁦11:44⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Reem Al-Qabbani · Portfolio manager

    Approved · ⁦2025-10-13⁩ at ⁦12:51⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-15⁩ at ⁦12:03⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-10-16⁩ at ⁦14:05⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-26⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Rana Al-Samman

  2. V1Returned for edit⁦2025-10-05⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Rana Al-Samman

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close