Project status card
28 October 2026
Preparing the 2026–2028 Medium-Term Plan & Governorate Plans
PRJ-2026-028 · Strategy & National PMO Sector · Strategic · WP-2026-028
- Progress
- 70% / 68%
- SPI · CPI
- 1.03 · 1.00
- Spend
- SYP 56M / SYP 80M
- Estimate at completion
- SYP 80M
Schedule
Planned to date 68%
Forecast finish: 2026-12-15 · On time
SPI1.03Schedule performance index · 1.03CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-27 · Up to date
Deliverables
5 of 7 due deliverables accepted on time (71%)
Next milestones
- Testing & acceptance complete2026-11-22
- Final handover2026-12-15
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 80M: 1 on track and 0 red or critical. Weighted progress is 70% against 68% planned, spend SYP 56M, and EAC SYP 80M (SYP 0K under).
No project is more than a month behind baseline.