Project status card
28 October 2026
Suwayda Drinking-Water Network from Al-Ain Dam
PRJ-2026-025 · Local Development & Governorates Sector · Operational · WP-2025-025
- Progress
- 36% / 35%
- SPI · CPI
- 1.03 · 1.02
- Spend
- SYP 370.6M / SYP 1.1B
- Estimate at completion
- SYP 1B
Schedule
Planned to date 35%
Forecast finish: 2027-09-30 · On time
SPI1.03Schedule performance index · 1.03CPI1.02Cost performance index · 1.02Health dimensions
Last update: 2026-10-26 · Up to date
Deliverables
5 of 6 due deliverables accepted on time (83%)
Next milestones
- Build complete2027-02-06
- Testing & acceptance complete2027-06-30
- Final handover2027-10-04
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 1.05bn: 1 on track and 0 red or critical. Weighted progress is 36% against 35% planned, spend SYP 370.6M, and EAC SYP 1.03bn (SYP 20.6M under).
No project is more than a month behind baseline.