PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Suwayda Drinking-Water Network from Al-Ain Dam

PRJ-2026-025 · Local Development & Governorates Sector · Operational · WP-2025-025

In progressOn track4ExecutionProject manager: Eng. Rami Youssef · Sponsor: Eng. Bashir Al-Tai
Progress
⁦36%⁩ / ⁦35%⁩
SPI · CPI
1.03 · 1.02
Spend
SYP 370.6M / SYP 1.1B
Estimate at completion
SYP 1B

Schedule

⁦1%⁩ ahead⁦36%⁩

Planned to date ⁦35%⁩

Forecast finish: 2027-09-30 · On time

SPI1.03Schedule performance index · 1.03CPI1.02Cost performance index · 1.02

Health dimensions

On track

Last update: 2026-10-26 · Up to date

Deliverables

⁦5⁩ of ⁦6⁩ due deliverables accepted on time (⁦83%⁩)

Next milestones

  • Build complete2027-02-06
  • Testing & acceptance complete2027-06-30
  • Final handover2027-10-04

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 1.05bn: 1 on track and 0 red or critical. Weighted progress is 36% against 35% planned, spend SYP 370.6M, and EAC SYP 1.03bn (SYP 20.6M under).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. Rami Youssef in MunjazInternal

Status: On track ·Project page