PRJ-2026-024On track1Pre-startStage-GatePlannedDelivered by:Ministry of Administrative Development
Unified Government Contact Centre & AI Assistant
Add to watchlist
One number and contact centre for government services, with an Arabic AI assistant that answers questions, tracks requests and hands complex cases to the right officer.
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2028-12-31
On baseline
Pre-start·Stage 1 of 5
Next gate:Initiation4 November 2026
Pre-start · Current stagePre-start · Current stage
Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+118 days vs approved
Baseline (original = approved)2028-12-31
Current forecast2029-04-28
By earned schedule2033-08-26
Critical activities
12
of 16 open activities
Late activities
11
past their baseline finish
Schedule performance
0.00
earned ÷ planned value
Next milestone
in 256 days
Project plan approved
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2027
2028
2029
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Today
2029-04-280%
Unified Government Contact Centre & AI AssistantPlanned: 2027-01-03 → 2028-12-31Forecast: 2027-01-03 → 2029-04-28Float: 0d
Project plan & baselinePlanned: 2027-01-03 → 2027-04-13Forecast: 2027-01-03 → 2027-04-29Float: 0dDrag to change its dates+16
2027-07-110%
Monitoring & reportingPlanned: 2027-03-07 → 2027-06-15Forecast: 2027-03-17 → 2027-07-11Float: 0dDrag to change its dates+26
2027-07-110%
Project plan approvedPlanned: 2027-06-15 → 2027-06-15Forecast: 2027-07-11 → 2027-07-11Float: 657dDrag to change its datesProject plan approved