PRJ-2026-024On track1Pre-startStage-GatePlannedDelivered by:Ministry of Administrative Development

Unified Government Contact Centre & AI Assistant

Add to watchlist

One number and contact centre for government services, with an Arabic AI assistant that answers questions, tracks requests and hands complex cases to the right officer.

Budget (BAC)

SYP 2.8B

Actual cost

SYP 0

⁦0%⁩ of budget

Progress

⁦0%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 2.8B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

Pre-startStage ⁦1⁩ of ⁦5⁩

Next gate:Initiation4 November 2026

  1. Pre-start · Current stagePre-start · Current stage
  2. Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
  3. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

No baseline approved yet

The project is in Pre-start: the working plan is ready (⁦16 activities⁩, finish ⁦2029-04-28⁩, ⁦budget SYP 2⁩.⁦8B⁩). Save it as the first baseline and send it for approval; once approved it is locked and changes only through an approved change request.

  1. Working

    Working baseline

    v2.0-draftWorking draftVersion AVersion B
    Finish
    ⁦2029-04-28⁩
    Budget
    SYP 2.8B
    ⁦16⁩ activities

    The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.

    Created ⁦2026-10-28⁩ · by Eng. George Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

No approved baseline yet — measured against the working plan

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftThe working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.⁦2026-10-28⁩by Eng. George Haddad