PRJ-2026-022On track3PlanningStage-GateNot startedDelivered by:Planning and Statistics Authority

Population & Housing Census Preparation — Phase 1

Add to watchlist

Phase 1 of the census preparation: updating maps and enumeration areas, buying tablets, setting up field offices in the governorates and the pilot census.

Budget (BAC)

SYP 1.2B

Actual cost

SYP 23M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 1.2B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Population & Housing Census Preparation — Phase 1

PRJ-2026-022 · Statistics Sector · External · WP-2026-022

Not startedOn track3PlanningProject manager: Ayman Sabbagh · Sponsor: Eng. Khaled Al-Kayyali
Progress
⁦2%⁩ / ⁦2%⁩
SPI · CPI
1.00 · 1.00
Spend
SYP 23M / SYP 1.2B
Estimate at completion
SYP 1.2B

Schedule

On plan⁦2%⁩

Planned to date ⁦2%⁩

Forecast finish: 2028-03-31 · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-18 · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-01-08
  • Designs approved2027-04-08
  • Build complete2027-08-21
  • Testing & acceptance complete2028-01-03

Top risks

  • Confidentiality of individual census data under the statistics law9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 1.15bn: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SYP 23M, and EAC SYP 1.15bn (SYP 0K under).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Ayman Sabbagh in MunjazInternal

Status: On track ·Project page