Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-012On track4ExecutionAgileIn progressDelivered by:Planning and Statistics Authority

Ministries Performance Follow-up & National Dashboards

Add to watchlist

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

Budget (BAC)

SYP 245M

Actual cost

SYP 186.2M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SYP 245M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Periodic update — October 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
PSA-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-26⁩
DraftUPD-012-2026-10Periodic update — October 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Ministries Performance Follow-up & National Dashboards
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Nizar Abu Fakhr

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦76%⁩

+4 pts on the last period

Planned to date

⁦75%⁩

SPI

1.01

Actual cost

SYP 186.2M

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the September 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
On track
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2026-12-24⁩

The PM’s comment on the statusFilled by the project manager

On track, no material variance from the baseline.

Prefilled from the September 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
No open risks
CodeImpedimentSeverity
No open impediments

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

No support needed this period.

Prefilled from the September 2026 card — edit it if it changed

Includes financial supportAuto-filled
No

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

PMO check

Mariam Al-Zoubi

Later

Sponsor review & approval

Dr. Ziad Al-Atassi

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    PMO check

    Mariam Al-Zoubi · PMO — analyst

    Delegated to Dr. Reem Al-Qabbani

  2. Technical acceptance

    Sponsor review & approval

    Dr. Ziad Al-Atassi · Project sponsor

    Delegated to Dr. Reem Al-Qabbani

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold
Waiting on Nizar Abu Fakhr

Previous versions

Every version is kept with its status and what changed.

  1. V1DraftCurrent⁦2026-10-26⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Nizar Abu Fakhr

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close