Project status card
28 October 2026
Ministries Performance Follow-up & National Dashboards
PRJ-2026-012 · Strategy & National PMO Sector · Operational · WP-2025-012
- Progress
- 76% / 75%
- SPI · CPI
- 1.01 · 1.00
- Spend
- SYP 186.2M / SYP 245M
- Estimate at completion
- SYP 245M
Schedule
Planned to date 75%
Forecast finish: 2026-12-24 · On time
SPI1.01Schedule performance index · 1.01CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-27 · Up to date
Deliverables
6 of 8 due deliverables accepted on time (75%)
Next milestones
- Testing & acceptance complete2027-01-03
- Final handover2027-01-23
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 245M: 1 on track and 0 red or critical. Weighted progress is 76% against 75% planned, spend SYP 186.2M, and EAC SYP 245M (SYP 0K under).
No project is more than a month behind baseline.