Ministries Performance Follow-up & National Dashboards
Add to watchlistScorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.
Budget (BAC)
Actual cost
76% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-01-03 | 2026-01-27 | +24 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-03 | 2026-05-17 | +44 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-03 | 2026-09-03 | +62 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-01 | 2027-01-03 | +94 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-23 | +23 days | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
76%Awaiting acceptance
14%Not handed in
10%Deliverable flow
Display options
| Project plan & baseline012-D1 | 5% | CRT-012-01 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2025-11-18 | V1 | 3 of 3 |
| Monitoring & reporting012-D2 | 5% | CRT-012-02 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-01-03 | V1 | 3 of 3 |
| Current-state assessment012-D3 | 10% | CRT-012-03 | Approved | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-02-17 | V1 | 3 of 3 |
| Benchmarking012-D4 | 10% | CRT-012-04 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-04-03 | V1 | 3 of 3 |
| Target model012-D5 | 16% | CRT-012-05 | Approved | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-05-19 | V1 | 3 of 3 |
| Roadmap012-D6 | 15% | CRT-012-06 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2026-07-03 | V1 | 3 of 3 |
| Wave 1012-D7 | 15% | CRT-012-07 | Approved | Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy | Dr. Mais Al-Sibai | 2026-08-17 | V1 | 3 of 3 |
| Wave 2012-D8 | 14% | — | Submitted | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-10-01 | V1 | 1 of 3 |
| Knowledge transfer012-D9 | 5% | — | Draft | Dr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.sy | Dr. Mais Al-Sibai | 2026-11-16 | V0 | 0 of 3 |
| Final report012-D10 | 5% | — | Draft | Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy | Dr. Mais Al-Sibai | 2026-12-31 | V0 | 0 of 3 |
| Total · 10 | 100% |