Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-012On track4ExecutionAgileIn progressDelivered by:Planning and Statistics Authority

Ministries Performance Follow-up & National Dashboards

Add to watchlist

Scorecards for ministries and governorates and national dashboards on the analytics platform, fed by Munjaz and the Statistics Sector and presented to the national steering committee.

Budget (BAC)

SYP 245M

Actual cost

SYP 186.2M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SYP 245M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-10-26⁩
ApprovedCRT-012-07Wave 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Ministries Performance Follow-up & National Dashboards
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Nizar Abu Fakhr

1The deliverableAuto-filled

DeliverableAuto-filled
Wave 1
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Nizar Abu Fakhr
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦15%⁩
DueAuto-filled
⁦2026-08-17⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-012_4.1_v1.pdfV1Nizar Abu Fakhr⁦2026-08-02⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Mais Al-Sibai
Accepted byAuto-filled
Dr. Ziad Al-Atassi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Testing & acceptance complete
ContractAuto-filled
—
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nizar Abu FakhrHead, Monitoring, Evaluation & PerformanceSubmitted—⁦2026-08-02⁩ 13:46
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-08-03⁩ 13:58
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Ziad Al-AtassiProject ownerOn behalf of Dr. Mais Al-SibaiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-08-06⁩ 14:05
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-08-10⁩ 10:25
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-08-11⁩ 11:02

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-08-03⁩

Inspection & technical acceptance — owner

Dr. Ziad Al-Atassi

Approved⁦2026-08-06⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-08-10⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-08-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Nizar Abu Fakhr on ⁦2026-08-02⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-08-03⁩ at ⁦13:58⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Mais Al-Sibai · Project owner

    Approved · ⁦2026-08-06⁩ at ⁦14:05⁩ · On behalf of Dr. Mais Al-Sibai (Dr. Ziad Al-Atassi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-08-10⁩ at ⁦10:25⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-08-11⁩ at ⁦11:02⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-08-02⁩

    PRJ-2026-012_4.1_v1.pdf

    Nizar Abu Fakhr

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close