20 MW Qalamoun Solar Field Subtask Last item under this branch 2027-04-30 58% 20 MW Qalamoun Solar Field Planned: 2025-03-02 → 2027-04-30 Forecast: 2025-03-02 → 2027-04-30 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-25 100% Management & governance Planned: 2025-03-02 → 2025-08-12 Actual: 2025-03-02 → 2025-09-25
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-07 100% Project plan & baseline Planned: 2025-03-02 → 2025-06-10 Actual: 2025-03-02 → 2025-07-07
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-25 100% Monitoring & reporting Planned: 2025-05-04 → 2025-08-12 Actual: 2025-05-21 → 2025-09-25
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-25 100% Project plan approved Planned: 2025-08-12 → 2025-08-12 Actual: 2025-09-25 → 2025-09-25 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-03-03 100% Design & permits Planned: 2025-07-05 → 2025-12-15 Actual: 2025-08-08 → 2026-03-03
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-14 100% Detailed design Planned: 2025-07-05 → 2025-10-13 Actual: 2025-08-08 → 2025-12-14
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-03 100% Permits & approvals Planned: 2025-09-06 → 2025-12-15 Actual: 2025-10-27 → 2026-03-03
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-03 100% Designs approved Planned: 2025-12-15 → 2025-12-15 Actual: 2026-03-03 → 2026-03-03 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Civil works Planned: 2025-11-07 → 2026-06-21 Actual: 2026-01-14 → 2026-10-26
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-22 100% Site works & excavation Planned: 2025-11-07 → 2026-02-16 Actual: 2026-01-14 → 2026-05-22
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-09 100% Structure Planned: 2026-01-09 → 2026-04-19 Actual: 2026-04-04 → 2026-08-09
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Finishes Planned: 2026-03-13 → 2026-06-21 Actual: 2026-06-23 → 2026-10-26
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Build complete Planned: 2026-06-21 → 2026-06-21 Actual: 2026-10-26 → 2026-10-26 Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-05 7% MEP works Planned: 2026-05-14 → 2026-12-26 Forecast: 2026-05-14 → 2027-03-05 Float: 8d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-16 20% Supply Planned: 2026-05-14 → 2026-08-23 Forecast: 2026-05-14 → 2027-01-16 Float: 8d Drag to change its duration +146
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-09 0% Installation Planned: 2026-07-16 → 2026-10-24 Forecast: 2027-01-02 → 2027-02-09 Float: 8d Drag to change its dates +108
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-05 0% Testing & commissioning Planned: 2026-09-17 → 2026-12-26 Forecast: 2027-01-26 → 2027-03-05 Float: 8d Drag to change its dates +69
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-05 0% Testing & acceptance complete Planned: 2026-12-26 → 2026-12-26 Forecast: 2027-03-05 → 2027-03-05 Float: 56d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-04-30 0% Handover Planned: 2026-11-18 → 2027-04-30 Forecast: 2027-02-19 → 2027-04-30 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-29 0% Provisional acceptance Planned: 2026-11-18 → 2027-02-26 Forecast: 2027-02-19 → 2027-03-29 Float: 8d Drag to change its dates +31
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-22 0% Final acceptance Planned: 2027-01-20 → 2027-04-30 Forecast: 2027-03-15 → 2027-04-22 Float: 8d Drag to change its dates
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-30 0% Final handover Planned: 2027-04-30 → 2027-04-30 Forecast: 2027-04-30 → 2027-04-30 Float: 0d Drag to change its dates Final handover