PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-03-09⁩
ApprovedMTG-KO-010Kick-off — 20 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — 20 MW Qalamoun Solar Field
Date and timeAuto-filled
⁦2025-03-09⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Eng. Rami Youssef

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Salma Al-ZaimDeputy President, Finance, Administration & the Investment Plan
Eng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction Projects
Eng. Rami YoussefDirector, Renewable Energy & Environment Projects
Dr. Reem Al-QabbaniDirector, National Project Management Office
Eng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction Projects

2Roles

PersonRoleDuty
Salma Al-ZaimProject sponsorSponsors the project, decides escalations and material changes
Eng. Wassim Al-AzmProject ownerApproves the requirements and accepts the deliverables
Eng. Rami YoussefProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Wassim Al-AzmProject ownerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Rami Youssef⁦2025-08-12⁩Done
Designs approvedEng. Rami Youssef⁦2025-12-15⁩Done
Build completeEng. Rami Youssef⁦2026-06-21⁩Done
Testing & acceptance completeEng. Rami Youssef⁦2026-12-26⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-07-06⁩
Start confirmed
Salma Al-Zaim · ⁦2025-03-10⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-03-10⁩ 12:51
2Chair’s approval (sponsor)Technical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2025-03-11⁩ 12:30
3Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-03-12⁩ 10:25

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2025-03-12⁩

Chair’s approval (sponsor)

Salma Al-Zaim

Approved⁦2025-03-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Rami Youssef on ⁦2025-03-10⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-12⁩ at ⁦10:25⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2025-03-11⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-03-09⁩

    The minutes as taken

    Eng. Rami Youssef

Only one version so far.