PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2024-09-28⁩
ApprovedPRJ-2026-01020 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1The resultAuto-filled

Priority score

83 of 100

Class

P1

75–100

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩5.020.0
Development value⁦12%⁩5.012.0
Economic & social return⁦8%⁩5.08.0
Urgency⁦10%⁩4.89.5
Legal requirement⁦10%⁩1.61.5
Risk⁦7%⁩1.07.0
Complexity⁦6%⁩1.06.0
Resource requirement⁦5%⁩1.05.0
Impact on citizens & beneficiaries⁦14%⁩3.910.2
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩3.12.6
Total⁦100%⁩—83

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2024-09-28⁩ 10:19
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-09-30⁩ 14:53
3Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApproved—⁦2024-10-01⁩ 09:00
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-10-03⁩ 10:07

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2024-09-30⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2024-10-01⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-10-03⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2024-09-28⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-09-30⁩ at ⁦14:53⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2024-10-01⁩ at ⁦09:00⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-10-03⁩ at ⁦10:07⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2024-09-28⁩