PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-08-04⁩
ApprovedDMD-2026-01020 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1The proposalAuto-filled

TitleAuto-filled
20 MW Qalamoun Solar Field
Proposed byAuto-filled
Eng. Rami Youssef
DepartmentAuto-filled
Renewable Energy & Environment Projects Directorate
Submitted onAuto-filled
⁦2024-08-04⁩
Proposal numberAuto-filled
DMD-2026-010

2Justification

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

3Objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Stimulate growth, restore production and attract investment

Strategic objectives served

  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure
  • SO-1.1 — Stimulate growth, restore production and attract investment

4Expected benefits

KindBenefit
SustainabilitySolar energy generated — target 31000 MWh / year
Cost savingValue of energy delivered to the public grid — target 232.5 SYP million

5Cost & feasibility

Estimated cost

SYP 2.4B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 1.7B
Supervision & consultingSYP 337.5M
Internal teamSYP 215M
Contingency reserve (5%)SYP 120M
TotalSYP 2.4B

6Initial risks

RiskLevelProposed response
Lower world PV prices allow a larger field within the allocationMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2024-08-04⁩ 09:54
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-08-05⁩ 13:34
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-08-08⁩ 14:41
4Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-08-11⁩ 09:48
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-08-14⁩ 09:30
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-08-18⁩ 11:02

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-08-05⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-08-08⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2024-08-11⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-08-14⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-08-18⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Rami Youssef on ⁦2024-08-04⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-08-05⁩ at ⁦13:34⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-08-08⁩ at ⁦14:41⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2024-08-11⁩ at ⁦09:48⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-08-14⁩ at ⁦09:30⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-08-18⁩ at ⁦11:02⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-08-25⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Rami Youssef

  2. V1Returned for edit⁦2024-08-04⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Rami Youssef