e-Litigation & Judicial Notification Platform — Release 2
Add to watchlistRelease 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-10 | 2025-09-28 | +18 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-18 | 2026-01-19 | +32 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-16 | 2026-07-07 | +52 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-23 | 2026-10-26 | +64 days | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2026-11-30 | On time | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
91%Awaiting acceptance
5%Not handed in
4%Deliverable flow
Display options
| Project plan & baseline008-D1 | 5% | CRT-008-01 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2025-07-22 | V1 | 3 of 3 |
| Monitoring & reporting008-D2 | 4% | CRT-008-02 | Approved | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2025-09-10 | V1 | 3 of 3 |
| Business requirements008-D3 | 9% | CRT-008-03 | Approved | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2025-10-29 | V1 | 3 of 3 |
| Solution design008-D4 | 9% | CRT-008-04 | Approved | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2025-12-18 | V1 | 3 of 3 |
| Release 1008-D5 | 14% | CRT-008-05 | Approved | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-02-06 | V1 | 3 of 3 |
| Release 2008-D6 | 14% | CRT-008-06 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-03-27 | V1 | 3 of 3 |
| Integrations008-D7 | 14% | CRT-008-07 | Approved | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-05-16 | V1 | 3 of 3 |
| System testing008-D8 | 11% | CRT-008-08 | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-07-04 | V1 | 3 of 3 |
| User acceptance testing008-D9 | 11% | CRT-008-09 | Approved | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-08-23 | V1 | 3 of 3 |
| Training & change008-D10 | 5% | — | Under review | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-10-11 | V1 | 1 of 3 |
| Go-live & handover008-D11 | 4% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Dr. Nisreen Al-Shoufi | 2026-11-30 | V0 | 0 of 3 |
| Total · 11 | 100% |