PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

e-Litigation & Judicial Notification Platform — Release 2

PRJ-2026-008 · Legal Affairs · Strategic · WP-2025-008

In progressOn track4ExecutionProject manager: Kinan Azzam · Sponsor: Eng. Mustafa Al-Awa
Progress
⁦91%⁩ / ⁦90%⁩
SPI · CPI
1.01 · 1.02
Spend
SYP 410.4M / SYP 460M
Estimate at completion
SYP 451M

Schedule

⁦1%⁩ ahead⁦91%⁩

Planned to date ⁦90%⁩

Forecast finish: 2026-11-26 · On time

SPI1.01Schedule performance index · 1.01CPI1.02Cost performance index · 1.02

Health dimensions

On track

Last update: 2026-10-27 · Up to date

Deliverables

⁦7⁩ of ⁦10⁩ due deliverables accepted on time (⁦70%⁩)

Next milestones

  • Final handover2026-11-30

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 460M: 1 on track and 0 red or critical. Weighted progress is 91% against 90% planned, spend SYP 410.4M, and EAC SYP 451M (SYP 9M under).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Kinan Azzam in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close