Project status card
28 October 2026
e-Litigation & Judicial Notification Platform — Release 2
PRJ-2026-008 · Legal Affairs · Strategic · WP-2025-008
- Progress
- 91% / 90%
- SPI · CPI
- 1.01 · 1.02
- Spend
- SYP 410.4M / SYP 460M
- Estimate at completion
- SYP 451M
Schedule
Planned to date 90%
Forecast finish: 2026-11-26 · On time
SPI1.01Schedule performance index · 1.01CPI1.02Cost performance index · 1.02Health dimensions
Last update: 2026-10-27 · Up to date
Deliverables
7 of 10 due deliverables accepted on time (70%)
Next milestones
- Final handover2026-11-30
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 460M: 1 on track and 0 red or critical. Weighted progress is 91% against 90% planned, spend SYP 410.4M, and EAC SYP 451M (SYP 9M under).
No project is more than a month behind baseline.