PRJ-2026-004 · From item 2
Aleppo 230 kV Substations RehabilitationPlanned to date 92%
- SPI
- 0.74
- Forecast finish
- 2027-02-03
- Budget
- SYP 10.3B
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
Rulings on the Aleppo substations and Hama National Hospital; the unified platform corrective plan and a first reading of the 2027 investment plan.
Starts in
10 min2026-10-28 · 10:00
80 of 90 min
Approve the previous minutes
ApprovalDr. Reem Al-Qabbani
5 min
Direct payment to subcontractors on the Aleppo substations
DecisionEng. Abdulrahman Al-Kilani
20 min
Hama hospital claims: dispute board or settlement
DecisionEng. Fadi Al-Droubi
20 min
Unified e-services platform — updated corrective plan
DiscussionEng. Khaled Al-Kayyali
15 min
First reading of the 2027 investment plan
For informationRasha Al-Mudarres
15 min
Any other business
DiscussionDr. Samer Al-Daqqar
5 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Dr. Reem Al-Qabbani5 min
Direct payment to subcontractors on the Aleppo substations
DecisionPresented by Eng. Abdulrahman Al-Kilani20 minPRJ-2026-004
Needs a committee decision
Hama hospital claims: dispute board or settlement
DecisionPresented by Eng. Fadi Al-Droubi20 minPRJ-2026-007
Needs a committee decision
Unified e-services platform — updated corrective plan
DiscussionPresented by Eng. Khaled Al-Kayyali15 minPRJ-2026-014
First reading of the 2027 investment plan
For informationPresented by Rasha Al-Mudarres15 min2027 annual work plan
Any other business
DiscussionPresented by Dr. Samer Al-Daqqar5 min
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0307 · Omar Al-Nahhas
ACT-0321 · Huda Al-Dandal
Quorum: Four of five members, including the chair or a named deputy
At least 4 voting members needed
3 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-004 · From item 2
Aleppo 230 kV Substations RehabilitationPlanned to date 92%
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
PRJ-2026-007 · From item 3
Hama National Hospital Upgrade & ExtensionPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
PRJ-2026-014 · From item 4
Unified Government e-Services PlatformPlanned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Agenda item needing a decision · PRJ-2026-004
Direct payment to subcontractors on the Aleppo substationsFrom item 2
Agenda item needing a decision · PRJ-2026-007
Hama hospital claims: dispute board or settlementFrom item 3
Change request awaiting decision · CR-2026-004
Add civil-record transfer & record merge to the first releaseUnified Government e-Services Platform
Change request awaiting decision · CR-2026-005
Change order 7: medical gases and HVAC redesignHama National Hospital Upgrade & Extension
Change request awaiting decision · CR-2026-006
Extend the contract by 150 daysHama National Hospital Upgrade & Extension
Corrective plan awaiting approval · CP-2026-01
Unified Government e-Services PlatformCorrective plan awaiting approval · CP-2026-03
Hama National Hospital Upgrade & ExtensionISS-0113 · Aleppo 230 kV Substations Rehabilitation
FundingSYP 160M· Asked from: Authority Executive Council
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ISS-0109 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice, or to extend the supply period
ISS-0103 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Unified Government e-Services Platform
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the Ministry of Interior for a dedicated test environment for three months
CP-2026-01 · Unified Government e-Services Platform
PeopleSYP 24.5M· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
CP-2026-03 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice
ACT-0307 · Omar Al-Nahhas
ACT-0311 · Eng. Wael Al-Khawlani