Execution
Periodic update card
Progress, status, risks and support requested
- Form no.
- PSA-PMO-F07
- Template edition
- 2.2
- Version
- V1
- Form date
- 2026-09-02
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-021
- Project
- Deir ez-Zor Suspension Bridge Reconstruction
- Portfolio
- Reconstruction & Infrastructure Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Wael Al-Khawlani
1ProgressAuto-filled
From the live data: accepted deliverables, the schedule and finance on the period’s last day.
Actual progress
0%
Planned to date
0%
SPI
1.02
Actual cost
SYP 228.8M
Main achievements this periodFilled by the project manager
Work went to the approved plan for the period, with the due deliverables handed in.
2Status
- Overall healthAuto-filled
- On track
- StageAuto-filled
- Planning
- Forecast finishAuto-filled
- 2028-12-31
The PM’s comment on the statusFilled by the project manager
On track, no material variance from the baseline.
3Risks and impedimentsAuto-filled
| Code | Risk | Score | Owner |
|---|---|---|---|
| RSK-0046 | Bids 18% above the engineering estimate | 15 | Eng. Wael Al-Khawlani |
| Code | Impediment | Severity |
|---|---|---|
| No open impediments | ||
4Support requested
What the project needs from leadership or the committeesFilled by the project manager
No support needed this period.
- Includes financial supportAuto-filled
- No
Approval logChain: Periodic update approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction Projects | Submitted | — | 2026-09-02 11:50 |
| 2 | PMO check | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | The reading agrees with the schedule and finance. | 2026-09-03 13:10 |
| 3 | Sponsor review & approval | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2026-09-07 14:17 |
Signatures
PMO check
Mariam Al-Zoubi
Approved2026-09-03
Sponsor review & approval
Salma Al-Zaim
Approved2026-09-07