Project status card
28 October 2026
Deir ez-Zor Suspension Bridge Reconstruction
PRJ-2026-021 · Development Projects Follow-up Sector · Strategic · WP-2026-021
- Progress
- 2% / 2%
- SPI · CPI
- 1.00 · 1.00
- Spend
- SYP 260M / SYP 13B
- Estimate at completion
- SYP 13B
Schedule
Planned to date 2%
Forecast finish: 2028-12-31 · On time
SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-23 · Up to date
Deliverables
1 of 1 due deliverables accepted on time (100%)
Next milestones
- Project plan approved2027-02-16
- Designs approved2027-07-04
- Build complete2028-01-27
- Testing & acceptance complete2028-08-21
Top risks
- Bids 18% above the engineering estimate15
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 13bn: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SYP 260M, and EAC SYP 13bn (SYP 0K under).
No project is more than a month behind baseline.