PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Deir ez-Zor Suspension Bridge Reconstruction

PRJ-2026-021 · Development Projects Follow-up Sector · Strategic · WP-2026-021

Not startedOn track3PlanningProject manager: Eng. Wael Al-Khawlani · Sponsor: Salma Al-Zaim
Progress
⁦2%⁩ / ⁦2%⁩
SPI · CPI
1.00 · 1.00
Spend
SYP 260M / SYP 13B
Estimate at completion
SYP 13B

Schedule

On plan⁦2%⁩

Planned to date ⁦2%⁩

Forecast finish: 2028-12-31 · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-23 · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-02-16
  • Designs approved2027-07-04
  • Build complete2028-01-27
  • Testing & acceptance complete2028-08-21

Top risks

  • Bids 18% above the engineering estimate15

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 13bn: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SYP 260M, and EAC SYP 13bn (SYP 0K under).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. Wael Al-Khawlani in MunjazInternal

Status: On track ·Project page