Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-017At risk5ClosureWaterfallIn progressDelivered by:Ministry of Finance

Ministry of Finance e-Archiving

Add to watchlist

Electronic archiving of the Ministry of Finance’s documents and financial correspondence, with a workflow for administrative correspondence and one search across the archive.

Budget (BAC)

SYP 355M

Actual cost

SYP 337.3M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 355M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-08-11⁩
RejectedCR-2026-015Add a classified-correspondence archive module

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Ministry of Finance e-Archiving
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Salma Al-Zaim
Project manager
Nour Al-Jabiri

1The change

TitleAuto-filled
Add a classified-correspondence archive module
KindAuto-filled
Deliverables
Requested byAuto-filled
Nour Al-Jabiri
Raised onAuto-filled
⁦2026-08-11⁩

Reason

A request to add a classified-correspondence module

Justification

Classified correspondence is handled on paper today

2Impact analysis

Cost

+SYP 16.3M

Schedule

+30 days

Risk

9 → 15

Benefits

+1%

Risk impact

Adds heavy security requirements at handover

Benefits impact

Limited: under 2% of correspondence

3The approval decision

The PMO’s recommendation

The national PMO recommends rejection; run the module as its own project

Change Committee decision
Reject
Decided on
⁦2026-08-25⁩
Decision number
DEC-2026-023

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nour Al-JabiriDirector, Government Systems & IntegrationSubmitted—⁦2026-08-11⁩ 09:24
2Project managerTechnical acceptanceNour Al-JabiriProject managerApproved—⁦2026-08-12⁩ 11:08
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-08-16⁩ 12:15
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-08-18⁩ 10:43
5Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeRejected—⁦2026-08-19⁩ 09:36

Signatures

Project manager

Nour Al-Jabiri

Approved⁦2026-08-12⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-08-16⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-08-18⁩

Change Committee

Dr. Ziad Al-Atassi

Rejected⁦2026-08-19⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Nour Al-Jabiri on ⁦2026-08-11⁩

  1. Technical acceptance

    Project manager

    Nour Al-Jabiri · Project manager

    Approved · ⁦2026-08-12⁩ at ⁦11:08⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-08-16⁩ at ⁦12:15⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-08-18⁩ at ⁦10:43⁩

  4. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Delegated to Dr. Reem Al-Qabbani

    Rejected · ⁦2026-08-19⁩ at ⁦09:36⁩

Steps that do not apply to this record

  • Contractual impact — the condition «Contract link?» does not hold
  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

The form was rejected and its path closed.

Previous versions

Every version is kept with its status and what changed.

  1. V1RejectedCurrent⁦2026-08-11⁩

    The request as raised

    Nour Al-Jabiri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close