Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-08-11
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-017
- Project
- Ministry of Finance e-Archiving
- Portfolio
- Government Digital Infrastructure & Systems Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Nour Al-Jabiri
1The change
- TitleAuto-filled
- Add a classified-correspondence archive module
- KindAuto-filled
- Deliverables
- Requested byAuto-filled
- Nour Al-Jabiri
- Raised onAuto-filled
- 2026-08-11
Reason
A request to add a classified-correspondence module
Justification
Classified correspondence is handled on paper today
2Impact analysis
Cost
+SYP 16.3M
Schedule
+30 days
Risk
9 → 15
Benefits
+1%
Risk impact
Adds heavy security requirements at handover
Benefits impact
Limited: under 2% of correspondence
3The approval decision
The PMO’s recommendation
The national PMO recommends rejection; run the module as its own project
- Change Committee decision
- Reject
- Decided on
- 2026-08-25
- Decision number
- DEC-2026-023
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Nour Al-JabiriDirector, Government Systems & Integration | Submitted | — | 2026-08-11 09:24 |
| 2 | Project manager | Technical acceptance | Nour Al-JabiriProject manager | Approved | — | 2026-08-12 11:08 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-08-16 12:15 |
| 4 | Financial impact | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-08-18 10:43 |
| 5 | Change Committee | Technical acceptance | Dr. Ziad Al-AtassiChange Committee | Rejected | — | 2026-08-19 09:36 |
Signatures
Project manager
Nour Al-Jabiri
Approved2026-08-12
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-08-16
Financial impact
Rasha Al-Mudarres
Approved2026-08-18
Change Committee
Dr. Ziad Al-Atassi
Rejected2026-08-19