The central decision log with reasons, impact and affected projects.
across 7 committees
since 2026-09-28
conditions being tracked
in the next two weeks
their tasks or follow-up are past due
this year
Every decision: what was decided, when, by whom, in which committee, why, its impact, its documents and the projects it affects.
Every escalation with its rung, its reason and the support asked: the kind, the amount, from whom, and the decision that answered it.
ESC-2026-021Awaiting decisionExecutive Council
ISS-0113Site workers stopped 4 days over late wagesAleppo 230 kV Substations Rehabilitation
Labour at the Aleppo substations site stopped for four days over late wages; risk RSK-0021 is at 25 of 25
Raised 2026-10-28To: Authority Executive CouncilIn 2 days2026-10-30
FundingSYP 160M· Asked from: Authority Executive Council
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ESC-2026-019Awaiting decisionExecutive Council
ISS-0109Finishing works in the new wing stopped — samples not approvedHama National Hospital Upgrade & Extension
Finishing works on the Hama hospital extension stopped over unapproved samples; the critical path slips every day
Raised 2026-10-27To: Authority Executive CouncilIn 5 days2026-11-02
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice, or to extend the supply period
ESC-2026-018Being acted onProgramme manager
ISS-0103Two vendor integration engineers withdrawn with no replacementUnified Government e-Services Platform
Two vendor integration engineers withdrawn; team velocity halved
Raised 2026-10-25To: Change CommitteeIn 12 days2026-11-09
PeopleSYP 24.5M· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ESC-2026-016Being acted onPMO director
ISS-0101Shared civil-registry test environment down for 9 daysUnified Government e-Services Platform
The shared civil-registry test environment has been down for nine days and integration testing is fully blocked
Raised 2026-10-26To: Dr. Reem Al-QabbaniIn 7 days2026-11-04
Coordination· Asked from: Dr. Samer Al-Daqqar
A letter from the President of the Authority to the Ministry of Interior for a dedicated test environment for three months
ESC-2026-015Awaiting decisionPMO director
ISS-0116Excavation clashes with the high-voltage line in block 4Darayya Replacement Housing
Excavation in block 4 of the Darayya housing site clashes with an undocumented high-voltage line
Raised 2026-10-25To: Dr. Reem Al-QabbaniIn 11 days2026-11-08
Coordination· Asked from: Eng. Wassim Al-Azm
Urgent coordination with the electricity transmission & distribution establishment to divert the line within 30 days
ESC-2026-014Awaiting decisionPMO director
ISS-0121Foundation works stopped awaiting works approvalsSheikh Najjar Industrial City Rehabilitation
Foundation works on the Sheikh Najjar northern plots stopped waiting for Aleppo Governorate’s works approvals
Raised 2026-10-26To: Dr. Reem Al-QabbaniIn 8 days2026-11-05
An approval· Asked from: Eng. Bashir Al-Tai
A Deputy President’s letter to Aleppo Governorate to speed up the approvals