Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
+SYP 28.3M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-11-26 | 2026-01-28 | +63 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-23 | 2026-06-13 | +110 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-06 | 2026-11-13 | +130 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-03 | 2026-12-15 | +73 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-16 | +16 days | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
62%Awaiting acceptance
10%Not handed in
28%Deliverable flow
Display options
| Project plan & baseline016-D1 | 5% | CRT-016-01 | Approved | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Eng. Mustafa Al-Awa | 2025-10-13 | V1 | 3 of 3 |
| Monitoring & reporting016-D2 | 5% | CRT-016-02 | Approved | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2025-11-26 | V1 | 3 of 3 |
| Business requirements016-D3 | 10% | CRT-016-03 | Approved | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-01-10 | V1 | 3 of 3 |
| Solution design016-D4 | 10% | CRT-016-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-02-23 | V1 | 3 of 3 |
| Release 1016-D5 | 16% | CRT-016-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-04-09 | V1 | 3 of 3 |
| Release 2016-D6 | 16% | CRT-016-06 | Approved | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-05-23 | V1 | 3 of 3 |
| Integrations016-D7 | 10% | — | Under review | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-07-06 | V1 | 1 of 3 |
| System testing016-D8 | 8% | — | Draft | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-08-20 | V0 | 0 of 3 |
| User acceptance testing016-D9 | 8% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-10-03 | V0 | 0 of 3 |
| Training & change016-D10 | 6% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-11-17 | V0 | 0 of 3 |
| Go-live & handover016-D11 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mustafa Al-Awa | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |