Project status card
28 October 2026
National Statistical Indicators & Open Data Portal
PRJ-2026-016 · Statistics Sector · Strategic · WP-2025-016
- Progress
- 62% / 70%
- SPI · CPI
- 0.89 · 0.95
- Spend
- SYP 350.8M / SYP 537.5M
- Estimate at completion
- SYP 565.8M
Schedule
Planned to date 70%
Forecast finish: 2027-01-18 · 18 days late
SPI0.89Schedule performance index · 0.89CPI0.95Cost performance index · 0.95Health dimensions
Last update: 2026-10-21 · Up to date
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2026-11-13
- Testing & acceptance complete2026-12-15
- Final handover2027-01-16
Top risks
- Too few accredited data owners in the ministries and governorates9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 537.5M: 0 on track and 0 red or critical. Weighted progress is 62% against 70% planned, spend SYP 350.8M, and EAC SYP 565.8M (SYP 28.3M over).
No project is more than a month behind baseline.