PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

National Statistical Indicators & Open Data Portal

PRJ-2026-016 · Statistics Sector · Strategic · WP-2025-016

In progressAt risk4ExecutionProject manager: Razan Al-Rifai · Sponsor: Eng. Khaled Al-Kayyali
Progress
⁦62%⁩ / ⁦70%⁩
SPI · CPI
0.89 · 0.95
Spend
SYP 350.8M / SYP 537.5M
Estimate at completion
SYP 565.8M

Schedule

⁦8%⁩ behind⁦62%⁩

Planned to date ⁦70%⁩

Forecast finish: 2027-01-18 · 18 days late

SPI0.89Schedule performance index · 0.89CPI0.95Cost performance index · 0.95

Health dimensions

At risk

Last update: 2026-10-21 · Up to date

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2026-11-13
  • Testing & acceptance complete2026-12-15
  • Final handover2027-01-16

Top risks

  • Too few accredited data owners in the ministries and governorates9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 537.5M: 0 on track and 0 red or critical. Weighted progress is 62% against 70% planned, spend SYP 350.8M, and EAC SYP 565.8M (SYP 28.3M over).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Razan Al-Rifai in MunjazInternal

Status: At risk ·Project page